Hi ALL
FYI: I got an update from our procurement
department about the status of the HRPPD deliveries:
the following is the revised schedule of
delivery conveyed to us by INCOM:
1 pc ship 12/15
1 pc ship 1/5
1 pc ship 1/19
1 pc ship 2/9
1 pc ship 2/23
this means a delay of 2.5 month to start (getting the first item) and a 18 day delay for the last one.
if this holds we should be still pretty ok. The try to make up the delay by eventually delivering 2 pieces
per month.