  • From: Thomas Ullrich <thomas.ullrich AT bnl.gov>
  • To: "eic-projdet-pfrich-l AT lists.bnl.gov" <eic-projdet-pfrich-l AT lists.bnl.gov>
  • Subject: [Eic-projdet-pfrich-l] Fwd: ePIC effort for TDR, DSC contribution
  • Date: Tue, 23 Jan 2024 10:08:24 -0500

FYI


-------- Forwarded Message --------
Subject: ePIC effort for TDR, DSC contribution
Date: Tue, 23 Jan 2024 13:38:56 +0100
From: Silvia Dalla Torre <Silvia.DallaTorre AT ts.infn.it>
To: eic-projdet-tic-l AT lists.bnl.gov
CC: John Lajoie <john.g.lajoie AT gmail.com>, jhuang AT bnl.gov <jhuang AT bnl.gov>, Garg, Prakhar <prakhar.garg AT yale.edu>, Barbosa Fernando <barbosa AT jlab.org>, Landgraf, Jeffery M. <jml AT bnl.gov>, Oleg Tsai <tsai AT physics.ucla.edu>, thomas ullrich <thomas.ullrich AT bnl.gov>, Ernst Sichtermann <EPSichtermann AT lbl.gov>, Nathaly Santiesteban <nathaly.santiesteban AT unh.edu>, matt posik <posik AT temple.edu>, Hartbrich, Oskar <hartbricho AT ornl.gov>, Simon Gardner <simon.gardner AT glasgow.ac.uk>, elke-caroline aschenauer <elke AT bnl.gov>



Dear DSLs,

     Following what has already been communicated at the ePIC collaboration meeting (Jan 9-13, 2024),
the DSLs are requested to prepare a TDR plan for their subsystem for calendar year 2024, including:

- The lab/testbeam/prototyping needed;
- The further progress needed for the reconstruction software;
- The verification of the implementation of the detector and detector response in simulation
and validation using information from lab/testbeam exercises or from literature;
- The studies required to demonstrate the detector performance;
- The required engineering design;
- The needed resources to achieve 60% (CD-2) and 90% (CD-3) design completion;
- The plan should include the time required to draft the text for the pre-TDR (CD-2) and TDR (CD-3).

The plan should present the activities required month by month in order to allow progress to be monitored.
The ultimate goal of this exercise should be 90% design completion
consistent with the requirements of the TDR and CD-3,
indicatively by the end of 2024.  We recognize that the available time is limited. Therefore, please make
an educated selection of the most essential studies doable within the available time.

We understand that a planning exercise like this will identify shortcoming in workforce and resources.
Those shortcomings should be clearly identified so everyone is aware and we can work together to address them.

The plans will be presented at dedicated CC WG meetings, to be organized by the CC WG conveners
over the next few weeks. The CC WG conveners will be asked to report on the status
of the planning at the TIC meeting on Monday Feb. 19.

Thank you,

Silvia, John, Oskar, Matt, Prakhar

--
Silvia DALLA TORRE
https://urldefense.com/v3/__http://wwwusers.ts.infn.it/*dallator/SilviaDALLATORRE/__;fg!!P4SdNyxKAPE!B64lEbGQ7-mVO8YD9CCTXGBh6qrQVH3EGoLzReRoG6D-UnqgLt_Kco0gCidlYlHhGWUe7QTPG8wObKW9nzS3FsdX2LtdbUdl6Ck$
INFN - Sezione di Trieste
https://urldefense.com/v3/__http://www.ts.infn.it__;!!P4SdNyxKAPE!B64lEbGQ7-mVO8YD9CCTXGBh6qrQVH3EGoLzReRoG6D-UnqgLt_Kco0gCidlYlHhGWUe7QTPG8wObKW9nzS3FsdX2LtdEh0Bx-0$ Via Valerio, 2
34127 Trieste ITALY


tel. +39.040.558 3360 - +39.040.375 6227
fax +39.040.558 3350 - +39.040.375 6258
e-mail: silvia.dallatorre AT ts.infn.it