Hi Everybody,
we have been asked by the sPhenix Project management to produce a document
to support the Outer Tracker project so it can be presented to BNL management and
DoE to obtain funding for the project.
We have a deadline of Nov 2 to produce this document.
There is an overleaf document set up for editing:
And example document showing the scope of the document requested
can be found here:
More detailed instructions from Ed O'Brien on the content of the document are listed below.
Since the time is short we should try to meet briefly later this week to touch
base and coordinate the writing process. Since sending out a doodle and collecting
responses will probably take too long we propose to use the time slot of the
General Meeting on Friday noon and the calibration task force executive meeting time slot
on Tuesday next week.
The indico agendas can be found here:
Friday:
Tuesday:
Please put all available text/material into the overleaf document well before Friday
so we can assess what we have.
Cheers
Takao and Christof
=======================================
Begin forwarded message:
From: Edward O'Brien <eobrien AT bnl.gov>
Subject: Management Plan for the Outer Tracker
Date: October 15, 2020 at 12:44:06 AM GMT+8
To: Hugo Pereira Da Costa <hugo.pereira-da-costa AT cea.fr>
Cc: "haggerty AT bnl.gov" <haggerty AT bnl.gov>, Glenn Young <glennyoung82251 AT gmail.com>, David Morrison <dave AT bnl.gov>, Gunther M Roland <rolandg AT mit.edu>, Ross Corliss <rcorliss AT mit.edu>, SABATIE Franck <Franck.Sabatie AT cea.fr>
Dear Hugo,
We would like to proceed to the next step in the
Outer Tracker effort, which in this case is to
prepare an Outer Tracker plan so that it is reviewable
for Cost, Schedule and required resources.
The sPHENIX Project Management team, and the co-spokespeople,
request that you draft an Outer Tracker Management Plan
similar to the sPHENIX MVTX Management Plan that I have attached.
I recommend that you aim for a concise 10-page version of the
MVTX plan. The document needs to include the project deliverables,
schedule, budget, labor resources and an org chart similar to what
is contained in the MVTX document. Much of sections 3.X and 4.X
in the MVTX document can be left out of the Management Plan for the
Outer Tracker, though we do need an org chart to define
responsibilities.
If we are going be successful in getting money from BNL for
this effort we are going to need a reviewable document that
contains the all of the aforementioned basic information that
we can share with BNL Management and DOE. I think that the
design and simulation effort for this detector is far enough
along that you can produce such a document.
We would like to receive this ~ 10-page document by November 2.
Please let me know if you have any questions. Thanks.
Ed
We would like to proceed to the next step in the
Outer Tracker effort, which in this case is to
prepare an Outer Tracker plan so that it is reviewable
for Cost, Schedule and required resources.
The sPHENIX Project Management team, and the co-spokespeople,
request that you draft an Outer Tracker Management Plan
similar to the sPHENIX MVTX Management Plan that I have attached.
I recommend that you aim for a concise 10-page version of the
MVTX plan. The document needs to include the project deliverables,
schedule, budget, labor resources and an org chart similar to what
is contained in the MVTX document. Much of sections 3.X and 4.X
in the MVTX document can be left out of the Management Plan for the
Outer Tracker, though we do need an org chart to define
responsibilities.
If we are going be successful in getting money from BNL for
this effort we are going to need a reviewable document that
contains the all of the aforementioned basic information that
we can share with BNL Management and DOE. I think that the
design and simulation effort for this detector is far enough
along that you can produce such a document.
We would like to receive this ~ 10-page document by November 2.
Please let me know if you have any questions. Thanks.
Ed
-
[Sphenix-calibration-l] [Urgent] Outer Tracker Management Plan,
Christof Roland, 10/20/2020
- Re: [Sphenix-calibration-l] [Urgent] Outer Tracker Management Plan, Takao Sakaguchi, 10/22/2020
Archive powered by MHonArc 2.6.24.