Skip to Content.
Sympa Menu

sphenix-emcal-l - [Sphenix-emcal-l] Initial setup at Fermilab

sphenix-emcal-l AT lists.bnl.gov

Subject: sPHENIX EMCal discussion

List archive

Chronological Thread  
  • From: John Haggerty <haggerty AT bnl.gov>
  • To: "sphenix-emcal-l AT lists.bnl.gov" <sphenix-emcal-l AT lists.bnl.gov>, "sphenix-hcal-l AT lists.bnl.gov" <sphenix-hcal-l AT lists.bnl.gov>
  • Subject: [Sphenix-emcal-l] Initial setup at Fermilab
  • Date: Sat, 17 Feb 2018 14:06:53 -0600

The initial setup of the calorimeters and DAQ are ready for next week's installation in the enclosure. Evidence that this is so:

https://photos.app.goo.gl/aonmy19NENH72jLy1

The EMCAL and Inner HCAL have data more or less as back at BNL. Martin helped me remotely to get ftbfbnl01, the gateway machine, on the network, and Todd helped me connect the machines in the staging area to that network.

The beam is back in MTEST as of last night. Looks like a go.

--
John Haggerty
email: haggerty AT bnl.gov
cell: 631 741 3358



  • [Sphenix-emcal-l] Initial setup at Fermilab, John Haggerty, 02/17/2018

Archive powered by MHonArc 2.6.24.

Top of Page