I put the document that I have for the Uniplast order here:
https://docdb.sphenix.bnl.gov/cgi-bin/private/ShowDocument?docid=10
Let me boil down the discussion from this morning to a few findings and action items.
- CU should get 4 SiPM's with the latest version of the preamps and the SiPM holder when they are available from BNL. [We didn't discuss this, but I think with the new preamps, you can in principle measure energies directly in pixels.]
- We will receive 10 (20?) "reference" (un-patterned) large tiles (1 m) as soon as Uniplast receives glue and ships them back to us (June?--we should check delivery).
- 21 cm width is the largest tile that can be produced at Uniplast at this moment; wider tiles than that will be glued on the long edge with optical cement.
- Lead time for tile production for the prototype is estimated to be 3 months. We must order them in August to be ready for the prototype.
Please correct any errors of fact or understanding.
--