The EMCAL and HCAL prototypes are installed on the MTEST beamline, thanks to Todd Nebel and his Fermilab crew, and the sizable sPHENIX group assembled here--Carter Biggs, Frank Toldo, and Steve Boose, who did much of the construction and assembly both here and at BNL, Eric Mannel, the T-1044 spokesperson, Megan Connors, who oversaw the HCAL prototype construction, Sean Stoll who oversaw the EMCAL construction,
and the whole group here today--Mickey Chiu, Edward Kistenev, Vera Loggins, Martin Purcshke, Mike Skoby, and Craig Woody, as well as Bob Azmoun and Tom Hemmick, here primarily for T-1037, which will share the beam.

The detectors were assembled on the beamline today, we saw decent LED's and leakage currents in the calorimeters, and we are well prepared for the Operational Readiness Clearance (ORC) review tomorrow afternoon.

More pictures of the detectors are here:

https://goo.gl/photos/wJzu9KgkwbJHcdsj9

--
John Haggerty
email: haggerty AT bnl.gov
cell: 631 741 3358