Skip to Content.
Sympa Menu

sphenix-l - [Sphenix-l] The sPHENIX Cost and Schedule Review is done

sphenix-l AT lists.bnl.gov

Subject: sPHENIX is a new detector at RHIC.

List archive

Chronological Thread  
  • From: EdwardOBrien <eobrien AT bnl.gov>
  • To: "sphenix-l AT lists.bnl.gov" <sphenix-l AT lists.bnl.gov>
  • Subject: [Sphenix-l] The sPHENIX Cost and Schedule Review is done
  • Date: Tue, 10 Nov 2015 19:04:05 -0500



Dear all,
We have just completed the Close Out of the sPHENIX Cost
and Schedule review. The review went well. The Close Out report
contained a complimentary assessment of the Project
status and a constructive list of recommendations.
Thanks to everyone that helped prepare us for the review
and advance the sPHENIX project in general. For the review, we
generated approximately 1000 pages in project related
documentation, gave 8 plenary talks and prepared 28 talks
for the breakout sessions.It was a good showing. Through
your great efforts, hard work and dedication sPHENIX
has been able to pass over this key hurdle.
Congratulations on your important accomplishment.

Ed



  • [Sphenix-l] The sPHENIX Cost and Schedule Review is done, EdwardOBrien, 11/10/2015

Archive powered by MHonArc 2.6.24.

Top of Page