Thanks to everyone who has continued to update the Conceptual Design Report in Overleaf. The document is here:
https://www.overleaf.com/8705585kvywfxxqyftr
and the Wiki has useful information about the document and deadlines:
https://wiki.bnl.gov/sPHENIX/index.php/CDR
We will have to freeze and tag the Conceptual Design Report for the Director's Review that is being held March 6-8 at BNL, and since it will need to be available to the committee about two weeks before, on February 20, it should then be available for collaboration review at least a week before, by February 12. The presentations and summaries of the technical reviews provide very useful input that can be included in the CDR.
Bottom line: please make any changes to the CDR by February 12.
I envision that we will want to modify the CDR after the Director's Review for the DOE CD-1 Review May 8-10, which implies another freeze about April 23, which should allow us to include some preliminary results from the spring beam tests.
--
John Haggerty