sphenix-magnet-l - Re: [Sphenix-magnet-l] Readiness to ship BaBar magnet

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: "Craddock, Wesley W." <wwc AT slac.stanford.edu>
  • To: "'John Haggerty'" <haggerty AT bnl.gov>, fabbric <Pasquale.Fabbricatore AT ge.infn.it>, "Racine, Mike" <racine AT slac.stanford.edu>, "Anerella, Michael D" <mda AT bnl.gov>
  • Cc: "Wisniewski, William J." <wjw AT slac.stanford.edu>, "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>, "Fouts, Ken" <kfouts AT slac.stanford.edu>
  • Subject: Re: [Sphenix-magnet-l] Readiness to ship BaBar magnet
  • Date: Mon, 28 Jul 2014 14:51:23 -0700

John,
I will attend your meeting this coming Wednesday. Just a few thoughts and
questions.

1) Will you be presenting shipping loads by truck as compared to the original
C5 delivery? If they are similar, I would suggest an analysis.

2) What about your thermal shield axial restraint. It looks better than,
the foam blocks that Mike Racine and I installed for moving the solenoid to
End Station A. However, the ends look "pointy". What is the impact of point
loads on the shield. I think you should do an analysis to verify that it is
OK. Although the shield is thin, it still has some substantial weight.

3) As I mentioned before, I am concerned about the valve control box,
particularly the heavy current leads.

Talk to you on Weds.

Wes




-----Original Message-----
From: John Haggerty [mailto:haggerty AT bnl.gov]
Sent: Monday, July 28, 2014 11:47 AM
To: fabbric; Craddock, Wesley W.; Racine, Mike; Anerella, Michael D
Cc: Kovach, Paul E; Wanderer, Peter; sphenix-magnet-l AT lists.bnl.gov; O'Brien,
Edward
Subject: Re: Readiness to ship BaBar magnet

Pasquale, Wesley, and Mike,

I have attached some slides from Paul Kovach about the work they've done in
the Superconducting Magnet Division about shipping the BaBar solenoid to BNL
which we plan to review this Wednesday, July 30. Because you three have so
much experience and history with the solenoid, I would like your input on
whether the magnet is ready to ship here, and whether there are any
additional precautions we should take before we set a ship date. I would ask
you to plan to summarize your findings, comments, and recommendations either
collectively or individually in email(s) to me afterward so we could consider
whether we should take any additional precautions.

BNL is now paying for BlueJeans videoconferencing, which you should be able
to connect to without any special hardware or software (although you will
need a decent network connection). If there are problems with the
connection, call or message me on skype (johnstonyb) and we'll move to that.
The meeting is

11am EDT
8am PDT
5pm CEST

and I have the start a little bit earlier in case of connection problems; I
think the meeting will be about an hour or perhaps a little more.

> BaBar Magnet Shipping Plan
> Wednesday July 30, 2014 * 10:45 a.m. EDT / 2 hrs, 45 minutes

> To join the Meeting:
> https://bluejeans.com/634168830
>
> To join via Browser:
> https://bluejeans.com/634168830/browser
>
> To join with Lync:
> https://bluejeans.com/634168830/lync
>
> To join via Cisco Jabber Video:
> https://bluejeans.com/634168830/jabber
>
> To join via Room System:
> Video Conferencing System: bjn.vc -or- 199.48.152.152 Meeting ID:
> 634168830
>
>
> To join via Phone:
> 1) Dial:
> +1 408 740 7256
> +1 888 240 2560 (US or Canada only)
> (see all numbers - http://bluejeans.com/numbers)
> 2) Enter Conference ID: 634168830
>

See or hear you on Wednesday.

On 7/18/14, 1:18 AM, fabbric wrote:
> John,
> July 30th at 17:00 is fine with me.
> I suppose we will use skype.
>
> Best regards
>
> Pasquale
>
> Il 17/07/2014 20:59, John Haggerty ha scritto:
>> Pasquale,
>>
>> I think I've touched base with everyone who should hear about this;
>> Mike Anerella unfortunately is out the week of July 28, but Paul
>> Kovach can do the presentation.
>>
>> Paul, if you can put some slides together by next Friday, July 25,
>> that will let them think about it in advance.
>>
>> I suggest we try for sometime on Wednesday, July 30, and if something
>> comes up, we can shift a day later.
>>
>> The time... difficult to accomodate all nine time zones; the best I
>> can see would be 8am at SLAC, 11am at BNL, and 5pm in Italy. Would
>> that work?
>>
>> On 7/16/14, 2:36 AM, fabbric wrote:
>>> John,
>>> the week of July 28 is fine to me.
>>> In the other two weeks I will be in vacation.
>>> However if you have material (slides, reports, ..), which can be
>>> circulated I can read and comment in any case.
>>>
>>> Best regards
>>>
>>> Pasquale
>>>
>>>
>>>
>>> l 15/07/2014 16:12, John Haggerty ha scritto:
>>>> Pasquale, Wesley, and Mike,
>>>>
>>>> I hope you're having a good summer--I'd like to see if we can
>>>> interrupt it for a couple of hours for you to look at what my
>>>> colleagues in the Magnet Division and I are envisioning for
>>>> shipping the BaBar solenoid to Brookhaven. We are hoping we can
>>>> complete our arrangements in this fiscal year (i.e., to ship at
>>>> least the solenoid itself before October 1), and I think we're on
>>>> track for that, but I think we should take a step back and discuss
>>>> our plans to make sure they make sense to you. A recent science
>>>> review of the project was quite positive, and we think we can
>>>> proceed with the next steps in shipping and testing the magnet.
>>>>
>>>> Of course, finding a time in mid-summer to do that is always
>>>> problematical. We may have to resort to a doodle poll, but as a
>>>> start, is there any time in the weeks of July 28, August 4, or
>>>> August
>>>> 11 that you could reserve around 2 hours for an engineering
>>>> evaluation of our plans?
>>>>
>>>> Thanks very much in advance for your past, and hopefully future,
>>>> willingness to help us with this.
>>>>
>>>
>>>
>>
>>
>
>


--
John Haggerty
email: haggerty AT bnl.gov
cell: 631 741 3358