[Sphenix-magnet-l] sPHENIX Magnet Biweekly meeting on July 29, 2015
- From: "Yip, Kin" <kinyip AT bnl.gov>
- To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Subject: [Sphenix-magnet-l] sPHENIX Magnet Biweekly meeting on July 29, 2015
- Date: Tue, 28 Jul 2015 16:00:55 +0000
We'll have our usual biweekly sPHENIX Magnet meeting on July29, 2015 @ 1pm in the 902 conference room.
Agenda and other materials may be found :
https://indico.bnl.gov/conferenceDisplay.py?confId=1296
Schedule R. Ceruti made new O-rings for 2 large doors on the vacuum vessel Vacation (Thur. to the end of next week) … Waiting for the work permit (H. Hocker) Measuring strain gauge before the Magnet Rotates (this Friday or next Monday ?)
Purchase orders: 40’ & 20’ LN2 VJ FLEX Line are already here To review quotes in 2 weeks (Aug. 10, 2015) on the He piping modification
Two action items (out of 13) of PCSS completed July 16: I sent a list of files to be copied to Windchill to Arno/Brown … Roberto has calculated the pressure given heat input … waiting for J. Sandberg or J. Muratore ?
J. Cozzolino’s ANSYS stress analysis on the sPHENIX Magnet (HCAL) It does seem that the difference in stress between cool-down only and full-current configuratioins is < 10%
|