sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: Kin Yip <kinyip AT bnl.gov>
  • To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
  • Subject: [Sphenix-magnet-l] The 10 remaining items in the ATS system have beem extended to Dec. 21, 2015
  • Date: Wed, 30 Sep 2015 18:06:52 -0400

Hi,

After the PCSS review, we have had 13 action items.  So far, we've performed 3.   Since our schedule is delayed (and
at least a few of those action items can be done only after the installation/set-up have been completed), the deadlines
in the ATS (Assessement Tracking System) for the 10 items have been extended to Dec. 31, 2015.   I list the items below.

Kin

8498.1.1 - LESHC 15-05 Review the sPHENIX Magnet (Testing) Action Item 1: Calculate temperature profile Open, Family=Institutional, DueDate=12/31/2015
8498.1.3 - LESHC 15-05 Review the sPHENIX Magnet (Testing) Action Item 3: Verify Design Calcs are correct Open, Family=Institutional, DueDate=12/31/2015
8498.1.6 - LESHC 15-05 Review the sPHENIX Magnet (Testing) Action Item 6: Verify vessel won't overpressurize Open, Family=Institutional, DueDate=12/31/2015
8498.1.7 - LESHC 15-05 Review the sPHENIX Magnet (Testing) Action Item 7: Ensure carbon steel anchored properly Open, Family=Institutional, DueDate=12/31/2015
8498.1.8 - LESHC 15-05 Review the sPHENIX Magnet (Testing) Action Item 8: Develop Green Sheet Open, Family=Institutional, DueDate=12/31/2015
8498.1.9 - LESHC 15-05 Review the sPHENIX Magnet (Testing) Action Item 9: Provide OP for new LN2 system Open, Family=Institutional, DueDate=12/31/2015
8498.1.10 - LESHC 15-05 Review the sPHENIX Magnet (Testing) Action Item 10: Verify ODH system functional Open, Family=Institutional, DueDate=12/31/2015
8498.1.11 - LESHC 15-05 Review the sPHENIX Magnet (Testing) Action Item 11: Have ESR/ASSRC reviews Open, Family=Institutional, DueDate=12/31/2015
8498.1.12 - LESHC 15-05 Review the sPHENIX Magnet (Testing) Action Item 12: Perform Magnet Safety Review Open, Family=Institutional, DueDate=12/31/2015
8498.1.13 - LESHC 15-05 Review the sPHENIX Magnet (Testing) Action Item 13: Verify piping installed Open, Family=Institutional, DueDate=12/31/2015