Hi,
Can I ask why there is a slip of one week ? Is this Nov. 13 really reliable this time ?
Have you guys talked with the ERL guys (Wencan Xu ?) about the start date of their solenoid replacement (Nov. 16) ?
Sent from my BNL Verizon Smartphone
------ Original message------
From: Orfin, Paul
Date: Thu, Nov 5, 2015 05:54
To: Yip, Kin;Mills, James A;
Cc: Than, Yatming (Roberto);
Subject:sPhenix Cryogenic lines
Gentlemen,
From my weekly vendor meeting I have an update on the line deliver dates. We will have a slip of about 1 week so the new delivery dates are as follows.
VJ spools for welding - 11/13/15 ship out date
Coax line - 11/23/15 ship out date
This means that we would start welding as early as 11/17/15 at ERL. This should be the same week the ERL plant will be down for repairs so this should work out well if there is no further delay of the VJ spools. The return line spool is complete and
the supply spool is about 30% complete. The coax line does not require any welding so once it comes in it can be installed immediately.
Thank you,
Paul Orfin
Cryogenic Systems, Collider-Accelerator Department
Brookhaven National Laboratory
Telephone: (631) 344-2899
Cryogenic Systems, Collider-Accelerator Department