sphenix-magnet-l - [Sphenix-magnet-l] Valve Box closed. ---- Cryo group piping ?

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: Kin Yip <kinyip AT bnl.gov>
  • To: "Ceruti, Raymond B" <rayc AT bnl.gov>
  • Cc: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
  • Subject: [Sphenix-magnet-l] Valve Box closed. ---- Cryo group piping ?
  • Date: Fri, 22 Jan 2016 11:47:23 -0500

Hi,

Thanks Ray for the update  (as below) !   I understand that you guys will calibrate the linear potentiometers in Bldg. 902 and next Wed. the riggers will
help move Piyush/Sonny's racks to Bldg. 912 (this was originally scheduled to be done today but it's changed as it's easier for Sonny et. al. to work in 902
than 912).

I haven't heard anything from the Cryo group about the small piping work yet ............

Kin

On 01/22/2016 11:13 AM, Ceruti, Raymond B wrote:

Hi Kin,

     Just an update on where we are with XPhenix.  Yesterday we closed the upper valve box doors.  I will be working with Sonny on getting the 4 position sensors calibrated and installed over the next couple of days.

 

Regards,

Ray  