sphenix-magnet-l AT lists.bnl.gov
Subject: sPHENIX discussion of the superconducting solenoid
List archive
[Sphenix-magnet-l] Brief Summary of the sPHENIX Magnet biweekly meeting (Aug. 16, 2017) at 1:30 pm at the 902 conf. room
- From: "Yip, Kin" <kinyip AT bnl.gov>
- To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Subject: [Sphenix-magnet-l] Brief Summary of the sPHENIX Magnet biweekly meeting (Aug. 16, 2017) at 1:30 pm at the 902 conf. room
- Date: Wed, 16 Aug 2017 21:42:22 +0000
Agenda/powerpoint : https://indico.bnl.gov/conferenceDisplay.py?confId=3470
(1)
We looked at D. Phillips latest layout :
(2)
We then discussed about the status since Ray Ceruti closed the doors for the junction-box at the Magnet/Extension end. We’re rigging power supply, (3)
Then, we talked about my optimistic scenario:
=> Install end-walls/roof-steel (more challenging due to the absence of J. Hock) => Move power supply/dump resistor & concrete blocks for the platform
ð D. Phillips hopes that the platform and hand railing will be installed by next Wed. Aug. 23 (if we can have the carpenters …)
=> Possibly install Valvebox on Sept. 1 or the week of Sept. 5 => Cryo piping/connection installation for ~4 weeks (possibly shorter) which can possible be shorter as some work already started and there may be more people available. => Cool-down by the end of Sept. (???) => If we’re “lucky”, High-Field Test may start in mid-Oct. if cool-down takes only ~2 weeks. (4)
John Haggerty then told us about the Director’s Review’s action item.
(5)
Jim Mills asked whether we need to review the “Run Plan”. We told him that the “Run Plan” has been reviewed in this meeting and also offline. Joe Muratore
|
- [Sphenix-magnet-l] Brief Summary of the sPHENIX Magnet biweekly meeting (Aug. 16, 2017) at 1:30 pm at the 902 conf. room, Yip, Kin, 08/16/2017
Archive powered by MHonArc 2.6.24.