sphenix-magnet-l AT lists.bnl.gov
Subject: sPHENIX discussion of the superconducting solenoid
List archive
[Sphenix-magnet-l] Best scenario for raising the magnet next week ... waiting for Dave's cable-tray layout
- From: Kin Yip <kinyip AT bnl.gov>
- To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Subject: [Sphenix-magnet-l] Best scenario for raising the magnet next week ... waiting for Dave's cable-tray layout
- Date: Fri, 22 Sep 2017 11:36:56 -0400
Hi, Attached is the PDF schedule of the Facility & Expt. Support Group for next week. Since we got the RFQ# only late Tuesday afternoon and Jon Hock communicated with the Central Shop this Wed. (Sept. 20) to make the Al cradle as soon as possible, the Central Shop told us that we may get it on Wed. So, in the above schedule and in the best scenario, we'll get the Al cradle on Wednesday and we assemble them on Thursday and then raise the Magnet (again) on Friday. [ Jon Hock has an operation next Wed. and I believe he won't be around to see the Magnet raise next Friday. ] From the PDF schedule, you can see also the scheduling for carpenters for "Handrail and stairs" every day next week. Nevertheless, that's only a desire/plan/hope or "on a best-effort basis". The same thing was scheduled for this week but we don't really get carpenters to work for us every day this week (eg. today, we don't seem to have carpenters), for different reasons :-( Richard Meier this morning has removed the cable which seems to be in the way of people walking up the lower staircase. PK/Dennis are waiting for Dave Phillips to draw the cable-tray layout so that we can install the cable tray (which would help Richard to route his cable, too). Kin From: Sanfilippo, Joseph W Sent: Friday, September 22, 2017 11:04:52 AM (UTC-05:00) Eastern Time (US & Canada) To: Bannon, Michael; Benante, John T; Ben-Zvi, Ilan; Bergh, Paul J; Campione, Lenny J; Christie, William; Cirnigliaro, Peter P; Donaldson, Dennis; Feng, Pei Kuan; Folz, Charles; Hamilton, Michael J; Hock, Jonathan; Karl, Francis X; Kobasiuk, Frederick D; Korol, Alex J; Lynch, Don; Pearson, Charles E; Phillips, David B; Pomaro, John; Pontieri, Stephen P; Rosas, Pablo J; Roser, Thomas; Sampson, Paul; Sanfilippo, Joseph W; Scaduto, Joseph; Hoffman, Caitlin; Seda, Thomas; Soja, Robert; Streckenbach, Brian; Vogt, Lawrence; White, John G; Zoccoli, Patrick Subject: FES Schedule for the week of Sept. 25, 2017 See attached file.
Joseph W. Sanfilippo Supervisor – Collider Accelerator Support Group Collider-Accelerator Department Office #: 631 344 7131 Pager #: 4180
|
Attachment:
FES Schedule for week of Monday, September 25, 2017, Open Jobs (by group).pdf
Description: Adobe PDF document