Skip to Content.
Sympa Menu

sphenix-magnet-l - Re: [Sphenix-magnet-l] Can we do hipot at 90-100K ? ---- How about Jan. 3 ?

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: "Yip, Kin" <kinyip AT bnl.gov>
  • To: "Schultheiss, Carl" <carls AT bnl.gov>
  • Cc: "Sandberg, Jon N" <jsandberg AT bnl.gov>, "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
  • Subject: Re: [Sphenix-magnet-l] Can we do hipot at 90-100K ? ---- How about Jan. 3 ?
  • Date: Tue, 2 Jan 2018 07:49:53 +0000

Hello Carl,

 

For the record, I’ve just attached another screenshot of the magnet temperatures (~102 K at this moment).  You can see that the temperature should fall below 100K sometime today.

 

We need to give time for Mike Lenz to install the box/barrier around the current leads (at the Valvebox).  In order to install the box, we need to connect the current

leads with MCM cables.  For that to happen, we need to finish the hipot.  

 

Since the cool-down to 4K won’t happen this week, I hope to make use of the time a bit more productively.   You don’t need to come in on Jan. 2, 2018.  But

can you please come in on Jan. 3 (as you originally plan anyway) to do the hipot at 90-something K ?   You have all the hours to do so as nothing else would happen

around the Magnet (while the Cryo group is working on the Plant).

 

Kin

 

From: Schultheiss, Carl
Sent: Monday, January 01, 2018 9:00 PM
To: Yip, Kin <kinyip AT bnl.gov>
Subject: RE: Can we do hipot at 90-100K ?

 

Hi,

   We could but the time required to hi-pot is 2 to 3 hours; if nothing is wrong. I would like to wait until
the temperature is lower, especially since we had an unusual event.
Since the magnet is not cold I may not be in on Jan 2nd.

Good Luck

Carl


From: Kin Yip [kinyip AT bnl.gov]
Sent: Friday, December 29, 2017 4:46 PM
To: Schultheiss, Carl; Muratore, Joseph
Subject: Can we do hipot at 90-100K ?

Hi,

As you can see below that, next week, the Magnet temperature will probably be stuck at 90-100 K (LN2 temperature).

Can we do the hipot at 90-100 K ??    The contraction from 100K to 4K is <10% (of the entirety).   This would save us a little bit of time.

Kin


-------- Forwarded Message --------

Subject:

[Sphenix-magnet-l] ODH ALARM in 912 cause problem to the He plant ... 4K next week doesn't look good

Date:

Fri, 29 Dec 2017 20:43:17 +0000

From:

Yip, Kin <kinyip AT bnl.gov>

To:

sphenix-magnet-l AT lists.bnl.gov <sphenix-magnet-l AT lists.bnl.gov>

CC:

Sandberg, Jon N <jsandberg AT bnl.gov>

 

Hi,

 

Roberto reported (email below) about a false ODH alarm which closed the LN2 supply valve and cause other damages.  The “vacuum skid”

didn’t concern us as we are not doing 2K Helium cool-down but only ~4K.  I attach the temperature profile from a sensor at the

superconducting bus and you could see when this “accident” happened --- the warm of a few K.

 

In any case, the Cryo group has shut down the (He) plant whereas the LN2 continues to cool to LN2 temperature.   They’re warming up the

Plant and hopefully, they’ll clear the “plug” (blockage) next week and cool-down the plant again.   The original plan of going to cool from

~90/100 K to 4K on Jan. 2, 2017 will not happen.  Since it’ll take a couple days to cool-down the plant itself, it’s not very likely we’ll see

4K next week.

 

I wonder whether we can do the “hipot” at ~90/100 K or so as there isn’t much contraction between 100K and 4 K anyway.

 

I also talked with Jonathan Reich and actually told what phone to “catch” Roberto.  There were actually two alarms.  He’s already replaced

the sensor in the “compressor room” which has nothing to do with the LN2 valve closing.   He’ll try to see whether he can replace the other

ODH alarm in 912 (which has been giving a lot of false alarms) next week while we’re still having cryo operation in 912.

 

Kin

 

From: Than, Yatming (Roberto)
Sent: Friday, December 29, 2017 12:27 PM
To: Yip, Kin
Cc: Orfin, Paul; Tuozzolo, Joseph E; Tallerico, Thomas N; Masi Jr, Leonard; Warkentien, Andreas F; Sardzinski, Mark A; Lederle, Dewey L; Talty, Patrick; Van Kuik, Brian; Soria, Victor
Subject: ODH ALARM 912

 

Kin,

 

We had an ODH alarm event in 912 around  overnight.

Shutdown the LN2 supply valve [automatic] into the bldg. to cryo plant and sPHENIX LN2 cooler.

 

The fans kicked on in the compressor room and temperature dropped sufficient and the water lines in the compressor room and water/oil heatexchangers on the vacuum skid cracked. The water tower eventually tripped on low water since the water was not returning to the tower.

Sullair helium compressor for the cryoplant tripped.

System is restarted but the cryoplant is not performing.

I have inlet pressure but the cold end of the plant and expander have to high inlet pressure.

Appears  I have plug in the plant.

So shut down plant.

 

We have next week to get the plant back up.

 

Roberto

 

 

 

 

Attachment: 2018-1-2 023640.JPG
Description: 2018-1-2 023640.JPG




Archive powered by MHonArc 2.6.24.

Top of Page