Skip to Content.
Sympa Menu

sphenix-magnet-l - Re: [Sphenix-magnet-l] AET spool delivery

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: "Yip, Kin" <kinyip AT bnl.gov>
  • To: "Orfin, Paul" <porfin AT bnl.gov>
  • Cc: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>, Glenn Young <glennyoung82251 AT gmail.com>
  • Subject: Re: [Sphenix-magnet-l] AET spool delivery
  • Date: Thu, 16 Apr 2020 18:08:36 +0000

Hi,

 

Thanks for letting me know.    I guess AET now has more time as we try to run RHIC in the summer …

 

Kin

 

From: Orfin, Paul <porfin AT bnl.gov>
Sent: Thursday, April 16, 2020 2:03 PM
To: Yip, Kin <kinyip AT bnl.gov>
Subject: AET spool delivery

 

Kin,

 

I received a schedule from AET.  The pipe spools will now come in at the end of July.  I am asking them for details on the change.  Despite this shift, we should still have no issue with the installation.  I am still assuming that the installation will occur after the end of the run in September.

 

Thank you,

Paul Orfin
Cryogenic Systems, Collider-Accelerator Department
Brookhaven National Laboratory
Building 1005S, MS 1005S, Room 220
Upton, NY 11973-5000
Telephone: (631) 344-2899
Fax: (631) 344-3329 
E-mail: porfin AT bnl.gov

 



  • Re: [Sphenix-magnet-l] AET spool delivery, Yip, Kin, 04/16/2020

Archive powered by MHonArc 2.6.24.

Top of Page