[Sphenix-magnet-l] Summary of today's meeting (Valvebox installation)
- From: "Yip, Kin" <kinyip AT bnl.gov>
- To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Subject: [Sphenix-magnet-l] Summary of today's meeting (Valvebox installation)
- Date: Mon, 21 Mar 2022 22:23:55 +0000
Hi,
Today at 3:30 pm, we had a meeting about the Magnet Valvebox installation. People attended include Mariana Albanese, Paul Orfin, Roberto Than, Jon Hock, Chris Runyan and Kin Yip.
One thing that I’ve learnt or become clear is: The end-caps need to be installed before the platform/deck can be installed. Only then can we install the Magnet Valvebox.
Below is the Minutes for today’s meeting about Valvebox installation --- written by R. Than and M. Albanese.
=================================================================================================
=================================================================================================
[ I’ve put it in the calendar: https://brookhavenlab.sharepoint.com/sites/sPHENIXMagnet/External/Lists/Calendar/DispForm.aspx?ID=283 ]
Kin
From: Than, Yatming (Roberto) <ythan AT bnl.gov>
Everyone, Notes from today's meeting. Marianna, Thank you for the meeting notes.
Thanks, Roberto
From:
Than, Yatming (Roberto)
I understand some of you had meeting with sPHENIX folks. Not sure how much has been discussed and planned. Schedule: Detailed schedule Do we need to discuss rigging onto platform? Manlift, scaffold?? Vacuum pumping system Leak check and pressure test Cable connections: Do you need Len Masi/Nils Danielson at this meeting?
________________________________________________________________________________ Microsoft Teams meeting Join on your computer or mobile app Join with a video conferencing device Video Conference ID: 119 125 602 6 Or call in (audio only) +1 518-641-1450,,742697611# United States, Albany Phone Conference ID: 742 697 611# ________________________________________________________________________________ |
Attachment:
sphenix magnet work meeting 3.21.2022.pptx
Description: sphenix magnet work meeting 3.21.2022.pptx
- [Sphenix-magnet-l] Summary of today's meeting (Valvebox installation), Yip, Kin, 03/21/2022
Archive powered by MHonArc 2.6.24.