Hi,
If we hear no objection, I believe, we’ll proceed to put on the “MLI” and then do the “hipot”.
Kin
From: Orfin, Paul <porfin AT bnl.gov>
All,
As an action from our last meeting, we conducted a total leak rate test. The results are promising and it seems we have repaired any significant leaks within the valve box. Please review the attached presentation and let us know if you agree so we can proceed with next steps in getting the valve box ready for 1008.
Thank you, Paul Orfin
|