Skip to Content.
Sympa Menu

sphenix-magnet-l - [Sphenix-magnet-l] VAT valve delay (Nov. ?!)

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: "Yip, Kin" <kinyip AT bnl.gov>
  • To: "Orfin, Paul" <porfin AT bnl.gov>
  • Cc: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>, Glenn Young <glennyoung82251 AT gmail.com>
  • Subject: [Sphenix-magnet-l] VAT valve delay (Nov. ?!)
  • Date: Wed, 4 May 2022 15:57:22 +0000

Hello Paul,

 

I called and talked with the buyer “Eleazer, Cheryl Ann eleazerc AT bnl.gov” and she had talked with Chintan.    The PO’s requested delivery date is May 30, 2022.

She told me that when the vendor sent her the acknowledgement letter ~Mar. 16 (for the PO 412132), the vendor didn’t mention the delay (Nov.) in the cover

letter and the delayed date was hidden somewhere else in the letter.   “Cunning ?!” …   So, she didn’t notice/pick up the Nov. date and thus she didn’t inform you.

 

Please let me/us know if you find a solution for this problematic delay (for the valves for the roughing pump etc.).

 

Kin