sphenix-magnet-l AT lists.bnl.gov
Subject: sPHENIX discussion of the superconducting solenoid
List archive
- From: Glenn Young <glennyoung82251 AT gmail.com>
- To: "Yip, Kin" <kinyip AT bnl.gov>
- Cc: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Subject: Re: [Sphenix-magnet-l] VAT valve delay (Nov. ?!)
- Date: Wed, 4 May 2022 12:17:45 -0400
Hello Paul,
I called and talked with the buyer “Eleazer, Cheryl Ann eleazerc AT bnl.gov” and she had talked with Chintan. The PO’s requested delivery date is May 30, 2022.
She told me that when the vendor sent her the acknowledgement letter ~Mar. 16 (for the PO 412132), the vendor didn’t mention the delay (Nov.) in the cover
letter and the delayed date was hidden somewhere else in the letter. “Cunning ?!” … So, she didn’t notice/pick up the Nov. date and thus she didn’t inform you.
Please let me/us know if you find a solution for this problematic delay (for the valves for the roughing pump etc.).
Kin
-
[Sphenix-magnet-l] VAT valve delay (Nov. ?!),
Yip, Kin, 05/04/2022
-
Re: [Sphenix-magnet-l] VAT valve delay (Nov. ?!),
Glenn Young, 05/04/2022
- Re: [Sphenix-magnet-l] VAT valve delay (Nov. ?!), Edward O'Brien, 05/04/2022
-
Re: [Sphenix-magnet-l] VAT valve delay (Nov. ?!),
Glenn Young, 05/04/2022
Archive powered by MHonArc 2.6.24.