[Sphenix-magnet-l] summary for the Permits/Interlocks for magnet test
- From: "Yip, Kin" <kinyip AT bnl.gov>
- To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Cc: "Vasquez, Joel" <jvasquez AT bnl.gov>
- Subject: [Sphenix-magnet-l] summary for the Permits/Interlocks for magnet test
- Date: Mon, 23 May 2022 15:30:35 +0000
Hi,
As Carl urges me, I write down all the permits and interlocks (that need to
be "GREEN"/OK) for the Magnet to start ramping and he will add more details
later :
(1) Cryo Permissive
(2) Cryo Interlock
(3) Crash Button - sPHENIX Control Room (interlock)
(4) Crash Button - Magnet Valvebox/Platform (interlock)
(5) Crash Button - sPHENIX IR Door (interlock)
(6) Water flow (interlock)
(7) Water temperature (interlock)
(8) Magnet pole-tip Door --- South (Permit)
(9) Magnet pole-tip Door --- North (Permit)
(10) sPHENIX Control Room (Permit)
We've planned for wiring the interlocks/permits (1-7).
I assume that Joel will have a sensor for South and North doors separately.
Talking with John Haggerty, I understand that Joel will provide the signal
wires/connections (3 pairs of wires) for 8-10 to 1008B. { Joel has already
helped us with (3) and
I imagine he may be able to connect to the same panel in 1008B. }