sphenix-magnet-l - [Sphenix-magnet-l] sequence of works when the Magnet Valvebox is on the floor of 1008

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: Kin Yip <kinyip AT bnl.gov>
  • To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
  • Subject: [Sphenix-magnet-l] sequence of works when the Magnet Valvebox is on the floor of 1008
  • Date: Mon, 6 Jun 2022 10:46:17 -0400

Hello All,

Carl Schultheiss, Ray Ceruti, Chris Runyan and I just had a meeting at 10-10:30 am to discuss the sequence of works to be done when the Magnet Valvebox is transported to the floor of 1008 (from 912).  Fred Kobasiuk kind of promised a slightly lower "stand" for the Valvebox than it's currently in 912 (so that it may be easier to do some little work).

The sequence of works need to be done is as follows :

-- near the end of the transport process (from 912 to 1008), Ray Ceruti will be there to take off the "can" covering the chimney of
the Valvebox

-- Ray will take off the restraints from the Valvebox

-- Carl will do the "hipot" on the Valvebox

-- Ray will work on putting back the heat-shield on one side of the Valvebox that's not accessible on the platform

-- With help from Frank Toldo's crew, Ray will direct to close one side of the Valvebox door (that's inaccessible on the platform)

-- Carl may/will do "hipot" again


As of now, we don't have a date for that transport yet.


Kin