Skip to Content.
Sympa Menu

sphenix-magnet-l - [Sphenix-magnet-l] Uniform resistances ... cables in 1008B mezzanine re-connected ... hipot tomorrow

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: "Yip, Kin" <kinyip AT bnl.gov>
  • To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
  • Cc: "Michnoff, Robert J" <michnoff AT bnl.gov>, "Chan, David" <dchan AT bnl.gov>, "Albanese, Marianna" <malbanese AT bnl.gov>
  • Subject: [Sphenix-magnet-l] Uniform resistances ... cables in 1008B mezzanine re-connected ... hipot tomorrow
  • Date: Fri, 7 Oct 2022 21:43:50 +0000

Hello,

Carl (and I) measured the resistances again for the 4 water-cooled-buses.  I attach the picture (with the results).  Now,  the Return pair seems to have ~10 Mohm and the Supply pair seems to have ~15 Mohm.
So, since the overall resistance is probably like 5 Mohm, our 520 V hipot would have around 100 micro-amp leakage current --- our hipot prediction 🙂     

We got the washers today (which I delivered to 1008B this morning) and nuts yesterday.  And as you can see below, the mechanical techs have re-connected those cables (that we disconnected a couple days ago)
this afternoon --- as I just came to check myself in 1008B mezzanine.   And they have also disconnected the braids on the platform.  Therefore, Carl and I would come in tomorrow to do a hipot for the water-cooled-buses.

Kin

From: Yip, Kin <kinyip AT bnl.gov>
Sent: Friday, October 7, 2022 5:28 PM
To: Karl, Robert F <rkarl AT bnl.gov>; Kobasiuk, Frederick D <kobasiuk AT bnl.gov>
Cc: Schultheiss, Carl <carls AT bnl.gov>; Rosas, Pablo J <rosas AT bnl.gov>
Subject: the MCM cables in 1008B mezzanine all re-connected !
 
Hello Rob and Fred,

I am at 1008B mezzanine and I've just checked.  It seems that Matt (?) has finished connecting all the MCM cables that we removed a couple days ago for measuring resistance !
Please let me know if you know something that I can't see 🙂   He's also removed the braids on the platform.

( Carl and I actually somehow met with Matt  in 1008B mezzanine this afternoon.   Carl gave his "instructions" to Matt with a sketch and demonstration for how to use the new nuts, 
washers in the way that Carl considers as the best way🙂

Please help us say "thank you" to him.

So tomorrow, Carl and I can do the hipot.

Kin

Attachment: 20221007_134041.jpg
Description: 20221007_134041.jpg



  • [Sphenix-magnet-l] Uniform resistances ... cables in 1008B mezzanine re-connected ... hipot tomorrow, Yip, Kin, 10/07/2022

Archive powered by MHonArc 2.6.24.