[Sphenix-magnet-l] 3 unresolved problems ... and sweep check tomorrow again (at 3 pm)
- From: "Yip, Kin" <kinyip AT bnl.gov>
- To: "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Cc: "Michnoff, Robert J" <michnoff AT bnl.gov>, "Albanese, Marianna" <malbanese AT bnl.gov>
- Subject: [Sphenix-magnet-l] 3 unresolved problems ... and sweep check tomorrow again (at 3 pm)
- Date: Wed, 19 Oct 2022 21:13:54 +0000
Hi,
I just left 1008B mezzanine and Pablo’s colleagues (Tim & Chris) were still working there when I left.
Carl and Pablo’s team together found a couple other problems (like a missing connection to the DCCT rack).
At the end of the day, when Carl left, they agree well --- the current goes
(ii) PSI problem in the power supply --- this is important because we need this working so that we can ramp the magnet from the Pet page as we plan/want to.
Ralph Schoenfeld and his new colleague came (iii) Tim/Chris still need to connect the Pole-tip door interlock signals.
Joel Vasquez gave them a new and more direct path (so that there is no intermediate processor which may cause problem).
So, they
So, even though we have run the Power Supply for more than 24 hours successfully (which is good !), we still need another day to finish solving the remaining issues, before we can connect the braids to the Magnet. ( We have to make Jesse Fite happy 😊 )
Kin
|
Attachment:
CURRENT.gif
Description: CURRENT.gif