Subject: sPHENIX discussion of the superconducting solenoid
List archive
Re: [Sphenix-magnet-l] Successful 24-hour run and successful ramp-down (slow discharge) ... final plan for tomorrow (morning only)
- From: "Mills, James A" <mills AT bnl.gov>
- To: "Yip, Kin" <kinyip AT bnl.gov>, "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
- Cc: "Michnoff, Robert J" <michnoff AT bnl.gov>, "Albanese, Marianna" <malbanese AT bnl.gov>
- Subject: Re: [Sphenix-magnet-l] Successful 24-hour run and successful ramp-down (slow discharge) ... final plan for tomorrow (morning only)
- Date: Thu, 27 Oct 2022 21:48:30 +0000
Excellent Kin! Many thanks to you and the team. Wonderful. Now you can relax a little. :-)
From: sPHENIX-magnet-l <sphenix-magnet-l-bounces AT lists.bnl.gov>
On Behalf Of Yip, Kin
Hi,
Our 24-hour run started at about 4:08 pm yesterday. Today at 4:13 pm, we started the normal ramp-down (slow discharge) which made use of the freewheeling diode inside the Magnet Power Supply and water-cooled-buses to release energy, mostly not through the dump resistor.
It took almost an hour (or about 51 minutes) to go from ~4620 to ~1000 A, at that point, we did a fast-discharge (by opening the contactors in the Dump Resistor and the energy was released through the Dump Resistor), so that we don't need to wait for another hour. The temperature rise for the magnet temperature is about only 2 K. I attach 2 plots to show what I've described above. This is a practice that BaBar did (their literature said fast-discharging at ~1300 A) and we did the same during the high-field test. We'll do this also in the future sPHENIX operation.
Tomorrow, CAS, Carl and I would try to ramp the magnet at 1.5 A/s once. If we succeed, we'll go to the top current and Roberto (Cryo) will try to do some small adjustment/tuning for 15 minutes or so at that current. If we fail, we will end anyway. ( Roberto can tune more next week during the mapping. )
After that, we can start installation for the mapper, open up the pole-tip doors etc.
Yours relatively very relaxedly,
Kin
|
-
[Sphenix-magnet-l] Successful 24-hour run and successful ramp-down (slow discharge) ... final plan for tomorrow (morning only),
Yip, Kin, 10/27/2022
- Re: [Sphenix-magnet-l] Successful 24-hour run and successful ramp-down (slow discharge) ... final plan for tomorrow (morning only), Mills, James A, 10/27/2022
- Re: [Sphenix-magnet-l] Successful 24-hour run and successful ramp-down (slow discharge) ... final plan for tomorrow (morning only), Edward O'Brien, 10/28/2022
Archive powered by MHonArc 2.6.24.