sphenix-magnet-l - Re: [Sphenix-magnet-l] Successful 24-hour run and successful ramp-down (slow discharge) ... final plan for tomorrow (morning only)

sphenix-magnet-l AT lists.bnl.gov

Subject: sPHENIX discussion of the superconducting solenoid

List archive

Chronological Thread  
  • From: Edward O'Brien <eobrien AT bnl.gov>
  • To: "Yip, Kin" <kinyip AT bnl.gov>, "sphenix-magnet-l AT lists.bnl.gov" <sphenix-magnet-l AT lists.bnl.gov>
  • Cc: "Michnoff, Robert J" <michnoff AT bnl.gov>, "Albanese, Marianna" <malbanese AT bnl.gov>
  • Subject: Re: [Sphenix-magnet-l] Successful 24-hour run and successful ramp-down (slow discharge) ... final plan for tomorrow (morning only)
  • Date: Fri, 28 Oct 2022 00:41:40 -0400

    Hi Kin,
     That was a very successful test. Thanks to you, Carl, Roberto,
    and everyone else in the CAD cryo group that made this happen.
    Of course many others in CAD contributed too. Instead of naming
    all 350 contributors, I'll just write congratulations to you all.
    Great job.

    Ed

On 10/27/22 5:41 PM, Yip, Kin wrote:
Hi,
Our 24-hour run started at about 4:08 pm yesterday.  Today at 4:13 pm, we started the normal ramp-down (slow discharge) which made use of the freewheeling diode inside the Magnet Power Supply and water-cooled-buses to release energy, mostly not through the dump resistor. 

It took almost an hour (or about 51 minutes) to go from ~4620 to ~1000 A, at that point, we did a fast-discharge (by opening the contactors in the Dump Resistor and the energy was released through the Dump Resistor), so that we don't need to wait for another hour.  The temperature rise for the magnet  temperature is about only 2 K.  I attach 2 plots to show what I've described above.  This is a practice that BaBar did (their literature said fast-discharging at ~1300 A) and we did the same during the high-field test.  We'll do this also in the future sPHENIX operation.


Tomorrow, CAS, Carl and I would try to ramp the magnet at 1.5 A/s once.   If we succeed, we'll go to the top current and Roberto (Cryo) will try to do some small adjustment/tuning for 15 minutes or so at that current.    If we fail, we will end anyway.  ( Roberto can tune more  next week during the mapping. ) 

After that, we can start installation for the mapper, open up the pole-tip doors etc.

Yours relatively very relaxedly,

Kin


_______________________________________________