Date: Thursday, August 31, 2017 at 08:35
To: sphenix-maps-l <sphenix-maps-l AT lists.bnl.gov>, sPHENIX LDRD <sphenix-ldrd AT lanl.gov>
Cc: "Ming Liu (ming AT bnl.gov)" <ming AT bnl.gov>, "Chamizo Llatas, Maria" <mchamizo AT bnl.gov>, Robert Redwine <redwine AT mit.edu>, Grazyna Odyniec <g_odyniec AT lbl.gov>, "Huang, Jin" <jhuang AT bnl.gov>, "XDong AT lbl.gov" <XDong AT lbl.gov>, Gunther Roland <rolandg AT mit.edu>, "Morrison, David" <morrison AT bnl.gov>
Subject: MVTX workfest Dec. 5-7 @Santa Fe
1. Solicit multiple theory predictions – December 2017
2. Refine the three key physics plots – October 2017
3. MoU with CERN for stave production – December 2017
4. Refine cost estimate with CERN – DONE
5. QA plan for tests (readout and cooling needs at LBNL and BNL) – October 2017
6. Cost of building two inner layers – DONE
7. Scenarios for repair and replacement – October 2017
8. Refine estimates for engineering design - End September- 2017
9. Include Cost of Extension cables – End September 2017
10. Consider including UV sterilization of demineralized water in cooling plant, October 2017
11. MoU with key production sites – December 2017
12. Optimize design of INTT and MVTX simultaneously – Feb-March 2018 – this will need sometime
13. Re-evaluate mechanical engineering costs once INTT and MVTX are final – after March 2018 (– too late?).
- related to #8 & #9, here one should make sure that the contingency is properly estimated to absorb cost variations due to different designs.
realistic contingency on carbon structures – End September 2017
14. Develop a Project Management Plan – September 2017, a draft available
– how detailed this plan needs to be at this stage of the project, further discussion with ALD/DOE. If PMP needed draft by October 2017
15. Clearly define scope, WBS dictionary, deliverables – October 2017
– not sure if all this is needed at this stage of the project, but can be done, further discussion with ALD/DOE
16. Evaluation and documentation of risks – October 2017-
[Sphenix-maps-l] MVTX DOE full proposal overleaf link,
Li, Xuan, 09/05/2017
- Re: [Sphenix-maps-l] MVTX DOE full proposal overleaf link, Rcf Phoenix, 09/06/2017
- <Possible follow-up(s)>
- [Sphenix-maps-l] MVTX DOE full proposal overleaf link, Xuan Li, 09/05/2017
Archive powered by MHonArc 2.6.24.