sphenix-maps-l - Re: [Sphenix-maps-l] MVTX DOE full proposal overleaf link

sphenix-maps-l AT lists.bnl.gov

Subject: sPHENIX MAPS tracker discussion

List archive

Chronological Thread  
  • From: Rcf Phoenix <xuanlipx AT rcf.rhic.bnl.gov>
  • To: "Li, Xuan" <xuanli AT bnl.gov>
  • Cc: sphenix-maps-l <sphenix-maps-l AT lists.bnl.gov>, sPHENIX LDRD <sphenix-ldrd AT lanl.gov>
  • Subject: Re: [Sphenix-maps-l] MVTX DOE full proposal overleaf link
  • Date: Wed, 6 Sep 2017 07:31:22 -0600

Dear All,
          Please use the overleaf link Listed in Ming's email. My link reaches the 60 file limitation.
           Thanks.
                                                       Xuan




On Sep 5, 2017, at 3:13 PM, Li, Xuan <xuanli AT bnl.gov> wrote:

Dear All,
          We would like to start the MVTX DOE full proposal preparation. The overleaf link has been updated to the following link with the full copy of the MVTX pre-proposal draft:
           You could directly go to this link to make relevant editing and updates. Or you could use git by 
               git clone https://git.overleaf.com/10918159syxjzkzxngfr
           Before you check in your editing, please check the latest update online.
           If you have any technical issues, please let me know.
           Look forward to a productive editing progress and a successful DOE proposal.
           Thanks.
                                                                                                 Xuan

From: <owner-sphenix-ldrd AT maillist.lanl.gov> on behalf of "Ming Liu (ming AT bnl.gov)" <ming AT bnl.gov>
Date: Thursday, August 31, 2017 at 08:35
To: sphenix-maps-l <sphenix-maps-l AT lists.bnl.gov>, sPHENIX LDRD <sphenix-ldrd AT lanl.gov>
Cc: "Ming Liu (ming AT bnl.gov)" <ming AT bnl.gov>, "Chamizo Llatas, Maria" <mchamizo AT bnl.gov>, Robert Redwine <redwine AT mit.edu>, Grazyna Odyniec <g_odyniec AT lbl.gov>, "Huang, Jin" <jhuang AT bnl.gov>, "XDong AT lbl.gov" <XDong AT lbl.gov>, Gunther Roland <rolandg AT mit.edu>, "Morrison, David" <morrison AT bnl.gov>
Subject: MVTX workfest Dec. 5-7 @Santa Fe

Dear all,

Following the very positive recommendations from the recent MVTX BNL Directors Review, we propose to move forward to prepare for the full proposal submission to DOE by early 2018 (~Jan. 2018?). 

After some discussions, we think a dedicated workfest in early December  before the sPHENIX Collaboration Meeting would be timely to push for the completion of the full proposal by the end of this year.

MVTX workfest: Dec. 5-7 (Tue-Thu.), 2017, Santa Fe, NM
sPHENIX Collaboration: Dec. 8-10, Santa Fe, NM

Here is a summary of action items and proposed timelines (draft, to be discussed with ALD and review committee ) following the Directors Review Recommendations:

1.     Solicit multiple theory predictions – December 2017 

2.     Refine the three key physics plots – October 2017 

3.     MoU with CERN for stave production – December 2017

4.     Refine cost estimate with CERN – DONE

5.     QA plan for tests (readout and cooling needs at LBNL and BNL) – October 2017

6.     Cost of building two inner layers – DONE  

7.     Scenarios for repair and replacement – October 2017 

8.     Refine estimates for engineering design -  End September- 2017 

9. Include Cost of Extension cables – End September 2017 

10.  Consider including UV sterilization of demineralized water in cooling plant,  October 2017

11.  MoU with key production sites – December 2017 

12.  Optimize design of INTT and MVTX simultaneously – Feb-March 2018 – this will need sometime

13.  Re-evaluate mechanical engineering costs once INTT and MVTX are final – after March 2018 (– too late?).

  - related to #8 & #9, here one should make sure that the contingency is properly estimated to absorb cost variations due to different designs.   

     realistic contingency on carbon structures – End September 2017

14.  Develop a Project Management Plan – September 2017, a draft available

     – how detailed this plan needs to be at this stage of the project, further discussion with ALD/DOE. If PMP needed draft by October 2017 

15.  Clearly define scope, WBS dictionary, deliverables – October 2017

  –  not sure if all this is needed at this stage of the project, but can be done, further discussion with ALD/DOE 

16.  Evaluation and documentation of risks – October 2017    
 

Maria, Grazyna, Bob, Xin, Jin  and Ming

-- 
Ming Xiong Liu
P-25, MS H846TEL: 505-667-7125 
Physics Division631-344-7821(BNL)
LANL630-840-5708(FNAL)
Los Alamos, NM 87545FAX:505-665-7020
_______________________________________________
sPHENIX-MAPS-l mailing list
sPHENIX-MAPS-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/sphenix-maps-l



Archive powered by MHonArc 2.6.24.

Top of Page