sphenix-maps-l - Re: [Sphenix-maps-l] sPHENIX stave production update

sphenix-maps-l AT lists.bnl.gov

Subject: sPHENIX MAPS tracker discussion

List archive

Chronological Thread  
  • From: Antonello Di Mauro <Antonio.Di.Mauro AT cern.ch>
  • To: "ming AT bnl.gov" <ming AT bnl.gov>
  • Cc: sphenix-mvtx-l <sphenix-maps-l AT lists.bnl.gov>, "ALICE-ITS-Upgrade-IB-sPHENIX \(Mailing list for ITS IB STAVE production for sPHENIX\)" <ALICE-ITS-Upgrade-IB-sPHENIX AT cern.ch>
  • Subject: Re: [Sphenix-maps-l] sPHENIX stave production update
  • Date: Thu, 11 Jun 2020 12:36:50 +0000

Dear Ming, all,

for sake of clarity, I proposed Thu 18, not today…

cheers

Antonello

On 6 Jun 2020, at 00:21, Ming Liu <ming AT bnl.gov> wrote:

Dear Antonello,
That is very good news! Yes, let meet next Thursday to discuss the stave production.
Have a good weekend.
 
Ming 
 
 
-- 
Ming Xiong Liu
P-25, MS H846                     TEL: 505-667-7125 
Physics Division                            631-344-7821(BNL)
LANL                                               630-840-5708(FNAL)
Los Alamos, NM 87545      FAX:  505-665-7020
 
 
From: Antonello Di Mauro <Antonio.Di.Mauro AT cern.ch>
Date: Friday, June 5, 2020 at 8:36 AM
To: "Ming Liu (BNL)" <ming AT bnl.gov>
Cc: sphenix-stave-l CERN <ALICE-ITS-Upgrade-IB-sPHENIX AT cern.ch>, sphenix-mvtx-l <sphenix-maps-l AT lists.bnl.gov>
Subject: sPHENIX stave production update
 
Dear Ming, all,
 
I hope you are all doing well.
 
I have some news concerning the restart of the stave production.
 
The DSF clean room has slowly been put back into operation, with a limited access and strict safety procedures.
This seems not to have a big impact on our activities as we were already fully equipped with coats, gloves, and masks and the max allowed people per project (two units) fits well our plans.
 
In the past two weeks two HICs (assembled before the lockdown) have been bonded and 8 staves have been glued, now they are being tested.
 
From next week Marcin will be back to CERN and we plan to resume also HIC assembly.
 
Last news concerns the export licence and end user certificate for the ALPIDE chip for sPHENIX, which have been delivered the past week.
 
I propose to have next meeting on Thu 18 at 17:00, I’ll circulate later the agenda and indico link.
 
Best regards
 
Antonello