Hi all,
The cables for commissioning the half-barrel will ship to LANL on 8/3/21 which is earlier than we predicted. It typically takes 2-3 days for samtec items to arrive at LANL and we have overnight shipping. We'll run local tests first then distribute the cables
to the required sites.
Cheers,
Cameron
Sent: 14 June 2021 11:59
To: Dean, Cameron Thomas
Cc: Ed Borys; Sondheim, Walter E; Ming Liu; Corrales Morales, Yasser
Subject: RE: [EXTERNAL]New samtec cable design (223041)
Hello Cameron,
Attached is final HDR assembly print.
The pinout table was updated to include reference to UCC8 pads on the standard ECUE transition boards.
UCC8 pad 3 is connected to GND and the other pads are not connected.
The order is scheduled to ship 8/3.
Thanks,
Jason
Samtec is the service leader in the electronic interconnect industry and a global manufacturer of Connectors, Cables, Optics and RF Systems, with full channel system support from the IC to the board and beyond.
|
This email and any appended documents are only for the intended person/entity and may contain information of Samtec, Inc., that is PRIVILEGED, PROPRIETARY, CONFIDENTIAL, AND/OR PROTECTED BY LAW. If you are not
the intended recipient you are hereby notified that any dissemination, disclosure, use or copying of this email or its contents is prohibited. If you this message in error, please notify Samtec immediately and delete the email, attachments and all copies.
The intended recipient should not disclose the content to third parties or reproduce the content without Samtec's written consent.
From: Jason Lambert
Sent: Thursday, June 10, 2021 2:25 PM
To: Dean, Cameron Thomas <ctdean AT lanl.gov>
Cc: Ed Borys <Ed.Borys AT samtec.com>; Sondheim, Walter E <sondheim AT lanl.gov>; Ming Liu <ming AT bnl.gov>; Corrales Morales, Yasser <ycorrales AT lanl.gov>
Subject: RE: [EXTERNAL]New samtec cable design (223041)
Thanks Cameron.
The order will be released from engineering hold and scheduled.
Regards,
Jason
From: Dean, Cameron Thomas <ctdean AT lanl.gov>
Sent: Thursday, June 10, 2021 1:48 PM
To: Jason Lambert <jason.lambert AT samtec.com>
Cc: Ed Borys <Ed.Borys AT samtec.com>; Sondheim, Walter E <sondheim AT lanl.gov>;
Ming Liu <ming AT bnl.gov>; Corrales Morales, Yasser <ycorrales AT lanl.gov>
Subject: Re: [EXTERNAL]New samtec cable design (223041)
Hello Jason,
I looked over the design and signal mapping which agrees with I was thinking about. I approve the design for release.
Many thanks,
Cameron
From: Jason Lambert <jason.lambert AT samtec.com>
Date: Wednesday, June 9, 2021 at 10:47 AM
To: "Dean, Cameron Thomas" <ctdean AT lanl.gov>
Cc: Ed Borys <Ed.Borys AT samtec.com>, "Sondheim, Walter E" <sondheim AT lanl.gov>,
Ming Liu <ming AT bnl.gov>, "Corrales Morales, Yasser" <ycorrales AT lanl.gov>
Subject: RE: [EXTERNAL]New samtec cable design (223041)
Hello Cameron,
Attached for your review is the updated assembly print for HDR-223041-XX-ECUE and copy of J2 PCB-111664-HDR-XX design file.
Please confirm if design is approved.
Once we have design approval the order will be released from engineering hold and scheduled.
Thanks,
Jason
Attachment:
HDR-223041-XX-ECUE.pdf
Description: HDR-223041-XX-ECUE.pdf
-
[Sphenix-maps-l] Fw: [EXTERNAL]New samtec cable design (223041),
Dean, Cameron Thomas, 06/14/2021
- <Possible follow-up(s)>
- Re: [Sphenix-maps-l] Fw: [EXTERNAL]New samtec cable design (223041), Liu, Ming Xiong, 06/14/2021
Archive powered by MHonArc 2.6.24.