Minutes shift change 2023-05-05
general
—————
- scaffolding inspected, bore access available (if you do work: be careful, put lock and remove it again, inform shift leader)
- no access Monday: roll-up day (access control system testing)
- still working on IRR/ORE approval
- CAD chief engineer said electrical systems are safe we can wait until next shutdown
- steps are Alex Tulio (Monday), Mike Lancy, site office (three days)
evening: Xuan
- EMCal NW chiller turned off (overheating)
- INTT work
night: Hanpu
- quiet, no alarms
- 1:00am INTT work done, LV, HV off
day: Sookhyun
- INTT experts replacing T readout box, T now reading correctly
- interlock work, still ongoing
- EMCal chiller replaced
- TPOT gas readings now normal
MBD (Mickey)
- HV scan last night
- set up remote scope in rack in preparation for timing in
HCal (Hanpu)
- cosmic runs during night
- weekend: cosmic running unless Martin is working on hit
- will ask help from shift crew
EMcal (Tim)
- took LED and single pixel noise data with bias, identified problems, will access to try to fix
TPOT (John K)
- need to sort out working vGTM —> Martin, John K, Hugo
TPC (Jin)
- Takao worked on automatically resetting FEEs, config ASIC, 626 FEEs working, everything but one FEE
- known felix problem
- John K and Jin diagnosed readout bottlenecks, addressing those with firmware updates
- expect 24 h operation, if gap that means pedestal data taking; if telemetry missing, shift crew don’t you worry
- observed three network outages in the last ~ 24 h
- not clear why
INTT (Itaru)
- replaced T readout board in North side, now T working properly
- no bore access needed
- taking data since this morning with full bias: calibration pedestal
- Raul and Martin will work on felix readout tonight
MVTX (Zhaozhong)
- technicians ran replacement signal cable today
DAQ
- see separate meeting
-
---------------------------------------------------------------------------------
Stefan Bathe
Stefan Bathe
Professor of Physics
Baruch College, CUNY
and RIKEN Visiting Scientist
Baruch: BNL:
17 Lexington Ave Bldg. 510
office 940 office 2-229
phone 646-660-6272 phone 631-344-8490
----------------------------------------------------------------------------------
Baruch College, CUNY
and RIKEN Visiting Scientist
Baruch: BNL:
17 Lexington Ave Bldg. 510
office 940 office 2-229
phone 646-660-6272 phone 631-344-8490
----------------------------------------------------------------------------------
-
---------------------------------------------------------------------------------
Stefan Bathe
Stefan Bathe
Professor of Physics
Baruch College, CUNY
and RIKEN Visiting Scientist
Baruch: BNL:
17 Lexington Ave Bldg. 510
office 940 office 2-229
phone 646-660-6272 phone 631-344-8490
----------------------------------------------------------------------------------
Baruch College, CUNY
and RIKEN Visiting Scientist
Baruch: BNL:
17 Lexington Ave Bldg. 510
office 940 office 2-229
phone 646-660-6272 phone 631-344-8490
----------------------------------------------------------------------------------
- [Sphenix-run-l] Minutes shift change 2023-05-05, Stefan Bathe, 05/05/2023
Archive powered by MHonArc 2.6.24.