[Sphenix-run-l] no beam in the night of May 30 (Tue.)
- From: "Yip, Kin" <kinyip AT bnl.gov>
- To: "Pontieri, Chris" <cpontieri AT bnl.gov>, "Toldo, Frank A" <fatoldo AT bnl.gov>
- Cc: "Costanzo, Timothy" <tcostanzo AT bnl.gov>, "Walker, Ronald" <rwalker AT bnl.gov>, "sphenix-run-l AT lists.bnl.gov" <sphenix-run-l AT lists.bnl.gov>, "Rosas, Pablo J" <rosas AT bnl.gov>
- Subject: [Sphenix-run-l] no beam in the night of May 30 (Tue.)
- Date: Thu, 25 May 2023 20:51:08 +0000
Hi, Frank and Chris,
As the email below shows (and I’ve made a phone call), the plan has changed such that there will be no beam on Tuesday even after Pablo finishes testing for the day.
This way, Wed. morning, we may go into the 1008-IR as early as we want, such that the installation of the blower can be done earlier and we do not need until 8 am. And Pablo and his team can continue to test/ramp the magnet hopefully soon after 8 am. ( Pablo needs to LOTO the Power Supply Tue. night. )
Kin
From: Lovelace III, Henry <hlovelace AT bnl.gov>
Quick change to Tuesday schedule 0730 sPHENIX will open
Sorry for any confusion.
Cheers, Henry
"Those who have finished by making all others think with them have usually been those who began by daring to think for themselves." From:
Lovelace III, Henry
Hi, The bridge block in front of the 56 MHz cryomodule needs to be removed from the 4 o'clock due the area needing additional procedures due to the space being classified as a class 2C confined space. The urgency is due to the availability of a two day maintenance period within this run and that the 56 MHz controls design will require full access to the cavity fundamental damper and other subsystems. With that, it has been proposed that Tuesday and Wednesday we dedicate time for not only the sPHENIX magnet ramp test but also to remove the bridge. The schedule for Tuesday and Wednesday becomes: Tuesday 05/30/23 sPHENIX magnet cooled sPHENIX solenoid ramp test starting at 0800 bridge block removal 4 o'clock No beam overnight Wednesday:
Cheers, Henry
(631) 344-5605 (Office) (757) 879-3915 (Cell)
Collider - Accelerator Department Electron-Ion Collider Accelerator Design
"To do my best, and let that stand the record of my brain and hand..."
|
- [Sphenix-run-l] no beam in the night of May 30 (Tue.), Yip, Kin, 05/25/2023
Archive powered by MHonArc 2.6.24.