sphenix-run-l - [Sphenix-run-l] INTT updated plot for INTT # of cluster vs. MBD Re: [Sphenix-l] Schedule for QM rehearsals tomorrow/no GM

sphenix-run-l AT lists.bnl.gov

Subject: Commissioning and running of sPHENIX

List archive

Chronological Thread  
  • From: shimomuramaya <maya AT cc.nara-wu.ac.jp>
  • To: "sphenix-l AT lists.bnl.gov" <sphenix-l AT lists.bnl.gov>
  • Cc: sphenix-run-l AT lists.bnl.gov
  • Subject: [Sphenix-run-l] INTT updated plot for INTT # of cluster vs. MBD Re: [Sphenix-l] Schedule for QM rehearsals tomorrow/no GM
  • Date: Fri, 1 Sep 2023 16:59:02 -0400

Dear Gunther, Dave, Ed and all,

Here is the updated INTT plot with the new noise cut.
Run number is 20708 which is same as the previous one.

This is the INTT # of clusters vs. MBD charge sum plots applying the timing
cut which selects the only the peaks of the upper right figure in the
attached 4-figure-slide. In the slide, the upper left figure is the previous
one which gets the preliminary and is in Ed’s slide now. The bottom left
figure is the same one just to make sure we reproduce the same tendency
without the timing cut, and the bottom right figure is the new one with the
timing selection. (made by Hinako)

The PDF version of left bottom figure is also attached.

We showed this in the shift change meeting today.
https://urldefense.com/v3/__https://docs.google.com/document/d/1798jqSqDPGcZVX_noT1h5PhBje7mIOAWX92t3blqf5o/edit__;!!P4SdNyxKAPE!E0vtIveZOkdtXWdOoxzIDeT-vHPjA7bjrRw28PgTtDm9C_K3mWjafLkpqIQ-IbF63cuj4GMzdNKU9avZ8PAGUPTf1YLuVoc$



Can you approve it as the updated preliminary plot?
If so, Hinako will send that plot with preliminary logo to the list soon.

Best regards,

Hinako, Takashi and Maya

Attachment: Shift_Change_MT.pdf
Description: Adobe PDF document



Attachment: QMBD_NclusINTT_cut_phx.pdf
Description: Adobe PDF document



###################
Associate Professor
Division of Natural Sciences
Nara Women's University

BNL Bldg.510C Room2-223

Email: maya AT cc.nara-wu.ac.jp
Office: 631-344-2778
Cell : 631-504-2144
###################

> 2023/08/31 16:23、Gunther M Roland via sPHENIX-l
> <sphenix-l AT lists.bnl.gov>のメール:
>
> Friends,
>
> Following the approval session on Wednesday and today's rehearsals (and
> considering also the many nice posters), we are in good shape for next
> week's QM conference - but we're not quite done yet. We will have second
> dry-runs for the plenary talk and the HF talk starting at 9AM tomorrow.
> Connection information can be found on the Indico page:
> https://indico.bnl.gov/event/20367/
>
> Thanks for the hard work that went into developing the material for these
> talks!
>
> After some discussion, we decided to cancel the general meeting tomorrow.
> While we are awaiting news on the RHIC repairs shortly, those are not
> available yet. We will summarize any news we have on this and other topics
> on slides posted on the Indico page linked above.
>
> Looking forward to seeing many of you in Houston next week!
>
> Best,
>
> Gunther and Dave
> _______________________________________________
> sPHENIX-l mailing list
> sPHENIX-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/sphenix-l




Archive powered by MHonArc 2.6.24.

Top of Page