Hello,

 

Probably after our “complaint”, the Access Control Group (ACG) of C-AD now keeps sending us the warning below when their work may impact 1008.    But since our 1008 IR/Assembly Hall and Gas Mixing House are

ODH areas anyway, so we should have been “familiar” with the ODH practice => get out if there is ODH alarm.

 

The ACG wants to finish installing ODH strobe light in 1008B before ~Jan. so that they can start scrubbing RHIC.

And then, they need to do the same for other service buildings 1002B …. 1012A before early Feb. in order to have the 45K wave going (if it’s allowed by the BHSO by then).

 

I just talked with Darren Hillis (the person who sent the email below).  They’re working in the weekends for this, definitely this Sat. and Sun.  They won’t work on Dec. 25 but they may work on Dec. 23/24  and then Dec. 26.

He claims at least 😊

 

Kin

 

From: Hillis, Darren <dhillis AT bnl.gov>
Sent: Friday, December 8, 2023 2:43 PM
To: Yip, Kin <kinyip AT bnl.gov>; Sampson, Paul <sampson AT bnl.gov>; Marr, Gregory <gmarr AT bnl.gov>; Bathe, Stefan <bathe AT bnl.gov>; Vasquez, Joel <jvasquez AT bnl.gov>; Reich, Jonathan <reich AT bnl.gov>; Toldo, Frank A <fatoldo AT bnl.gov>; Pisani, Robert <pisani AT bnl.gov>; Albanese, Marianna <malbanese AT bnl.gov>
Cc: Access Controls Group <accesscontrols AT bnl.gov>; Reich, Jonathan <reich AT bnl.gov>; Benante, John T <benante AT bnl.gov>; Giorgio, Caitlin <charper AT bnl.gov>
Subject: Work in building 1008B

 

All,

 

C-AD Technicians will be working in building 1008B running cables for new installation of ODH components tomorrow and the next day. There is not an anticipate effect on mode or any functions within 1008IR, but there is always this possibility when work is being performed.

 

I will call in the morning to leave messages as well at the following:

             Notify sPHENIX Control Room Shift Supervisor at x7815

Notify 911MCR Control Room Personnel at x4662

Notify CAS Support at x2024

            Notify Kin Yip @ x 4116

            Notify Frank Toldo @ x7788

 

Thanks,

 

 

Darren Hillis

Access Controls Group

Collider-Accelerator Department

Brookhaven National Laboratory

Upton, NY 11973 USA

W(631)344-5849

Cell(631)742-5081

dhillis AT bnl.gov

 