Hello,

 

Paul Sampson told me that they’re going to do the monthly ATS/generator/UPS test today as we haven’t done it for a month

(even though we got a power outage on Jan. 7 and the ATS worked at that time --- more than a test).

 

We should see nothing and hopefully, it’s as seamless as yesterday’s switchover from overhead to underground feed.

 