Hi INTT group,
That looks like excellent progress. Thanks for the update.

Ed

On 3/4/24 11:15 PM, nouicer wrote:
Dear Jim and John,

The work on the INTT south side is done, pedestal results with full bias can found at:

https://drive.google.com/file/d/1EhhVn4dYn2eylUitd7V65_r2E7u8oMwH/view?usp=drive_link

The INTT task-force is moving to the north side on March 5th, 2024.

Thank you very much for your help and supports.

Sincerely,
Kazuma F., Takahiro K., Jaein H., Raul C., Maya S., Akitomo E.,
Jeffrey H., Daniel C., Robert P., Stephen B., Genki N. and Rachid N.