star-fst-l AT lists.bnl.gov
Subject: Star-fst-l mailing list
List archive
Re: [Star-fst-l] Cost Estimate for Production FST Inner Signal Cables // Fwd: Re: integration of sTGC and Si
- From: Zhenyu Ye <yezhenyu2003 AT gmail.com>
- To: "Capotosto, Michael (CONTR)" <capotosto AT bnl.gov>
- Cc: "star-fst-l AT lists.bnl.gov" <star-fst-l AT lists.bnl.gov>
- Subject: Re: [Star-fst-l] Cost Estimate for Production FST Inner Signal Cables // Fwd: Re: integration of sTGC and Si
- Date: Tue, 2 Jul 2019 13:21:31 -0500
> On Jul 2, 2019, at 1:19 PM, Capotosto, Michael (CONTR) <capotosto AT bnl.gov>
> wrote:
>
> Gerard,
>
> Cable size should not be an issue, as the custom cable will almost
> certainly be smaller in diameter than three separate shielded cables.
>
> As far as requirements go, it is my understanding that the cables should be
> the same size as the test stand cables, coming in at 8' long +/- 1".
> Assuming we follow the quote from the IST cables: The cable will have 16
> pairs of 28AWG solid 2 conductor cabled together, at a minimum of 16 twists
> per foot. The cable will also have 4 individual conductors, size 22AWG
> stranded (7/30). The cable will be shielded with an aluminum/mylar tape,
> with a 25% minimum overlap, and a 22AWG stranded (7/30) drain wire. Is this
> correct? Are there any preferences for pair colors and outer jacket color?
>
> Do you know if FEP was a requirement for this cable? When assembling the
> T-Boards we had issues with the jacket beginning to melt, shrinking back,
> or splitting - would we be able to switch to an insulation with a higher
> melting point such as Teflon/PTFE?
>
> Zhenyu,
> Does the 48 cable count include spares? If not, how many spares do you
> need?
Hi Mike
We only need 36 good cables for the actual detector. So the rest 12 are
spares.
Zhenyu
>
> Thanks,
> Mike Capotosto
>
>
> -----Original Message-----
> From: Gerard Visser <gvisser AT indiana.edu>
> Sent: Tuesday, July 02, 2019 12:03 PM
> To: Capotosto, Michael (CONTR) <capotosto AT bnl.gov>
> Cc: star-fst-l AT lists.bnl.gov
> Subject: Re: [Star-fst-l] Cost Estimate for Production FST Inner Signal
> Cables // Fwd: Re: integration of sTGC and Si
>
> Hi Zhenyu, Mike,
> I send here below the info on the *IST* inner cable. Also the third
> attachment here (not part of the forwarded message below but following a
> few days later) was a refreshed quote for that.
> For *FST*, I think we will revise slightly (fewer pairs)... Also if
> necessary I think the power wires could be reduced from 22 AWG to 24 AWG as
> the current will be 2/3 that of IST and the length also less than IST. But
> someone should make some estimation of voltage drop. Of course 22 AWG is
> better if the diameter is OK.
> If I remember right, BNL purchased from Meunier for one of our past
> projects, and they have good pricing, so when you contact Alpha for the new
> cable design & quote you may want to suggest procurement through Meunier,
> unless BNL can buy direct from Alpha of course.
> Sincerely,
>
> Gerard
>
>
> On 7/2/2019 9:57 AM, Zhenyu Ye wrote:
>> Hi Mike,
>>
>> Can you please make a cost estimate for the actual FST inner signal
>> cables, based on the work you have done for the FST test cables? We will
>> need 48 of actual cables. The cost should include the cable itself (Gerard
>> had a quote for it. Gerard, can you please share it with Mike),
>> connectors, and external assembly work for the cable+T-board.
>>
>> Thanks,
>> Zhenyu
>> _______________________________________________
>> Star-fst-l mailing list
>> Star-fst-l AT lists.bnl.gov
>> https://lists.bnl.gov/mailman/listinfo/star-fst-l
>>
>
> ---------------------------------------------------------------------------------
> ---------------------------------------------------------------------------------
> -------- Forwarded Message --------
> Subject: Re: integration of sTGC and Si
> Date: Thu, 25 Oct 2018 14:15:12 -0400
> From: Gerard Visser <gvisser AT indiana.edu>
> To: Ye, Zhenyu <yezhenyu AT uic.edu>
> CC: Aschenauer, Elke <elke AT bnl.gov>, Scott W. Wissink <wissink AT indiana.edu>
>
> hi Zhenyu,
> I was wrong, sorry. That was not the latest quote, there was some
> design change after that one. I don't know the details but it drove up the
> cost. The actual last quote is attached here. We ordered 1500 ft on MIT PO
> # 4501543228. I do not have a copy of the PO. The final spec sheet signoff
> for partnumber 518222 is also attached here. If/when we get a new quote, we
> have to reference that.
> I hope this gives you enough info for now, apart from a requote which
> again I am happy to as for once I'm told the length.
> Sincerely,
>
> Gerard
>
>
> On 10/25/2018 1:53 PM, Gerard Visser wrote:
>> Hi Zhenyu,
>> I think I found the latest version of the quote that we ordered
>> against. I attach it here. I am still looking for some email thread about
>> the actual order.
>> If you know how much you would like to buy, I can request a new
>> quote. I believe the min is 1000 ft and increments must be 500 ft
>> (possibly must be 1000 ft).
>> Just FYI, this quote partnumber is not the actual partnumber,
>> which is set only after the first order. New quote I presume will be
>> showing the actual partnumber. (Which is I believe 518222.)
>>
>> Gerard
>>
>>
>> On 10/25/2018 11:23 AM, Gerard Visser wrote:
>>> hi Zhenyu,
>>>
>>> We should be able to re-use the patchpanel boards I hope? (Do you
>>> have them, or have located them?) These have (at least in IST they
>>> had) the voltage regulators on them, it is more than just a
>>> patchpanel. Who will design your frontend electronics boards?
>>> If it is necessary, same person can hopefully deal with patchpanels too I
>>> think?
>>>
>>> Probably some discussion is needed on scope of work for me for FST.
>>> It is likely I should not be volunteered to make the patchpanel board
>>> (and so better if he/she who will make it costs it now for you). I
>>> hope the frontend boards with APV are being costed by someone in
>>> detail now. Sorry that I may just not know about the state of this.
>>>
>>> I am of course able to help with design issues for the FEE, as I did
>>> help Ben Buck in the IST case. I will do my best to assist to have a
>>> good design, but am counting on your angineer(s) to do the most of this
>>> work.
>>>
>>> As to cable costs, I can find the old costs, I promised to do that
>>> but I haven't tracked it down yet, sorry. Probably if I put in a RFQ
>>> to same company I can get an updated cost from them with little
>>> effort - so for sure I don't mind to ask. A new quote will be much
>>> better for budget justification than the old one and a guess about
>>> inflation. But you have to give me a length, how much would you need
>>> in total? And connectors for the cable I hope you guys can cost? the
>>> partnumbers should be in Ben's documentation.
>>>
>>> Have all the long cables (between rack and patchpanel) been saved?
>>> (I.e. we don't have to cost replacing those?)
>>>
>>> I'll make an estimate for firmware and integration support manpower
>>> here. I've been dealing with FCS materials estimates first, but
>>> manpower for FST and FCS coming up now.
>>>
>>> Sincerely,
>>> Gerard
>>>
>>>
>>> On 10/25/2018 10:53 AM, Ye, Zhenyu wrote:
>>>> Hi Gerard,
>>>>
>>>> Thank you. Can you please send me the cost (including cables, new
>>>> patch panel boards, and manpower for possible firmware change)?
>>>>
>>>> Zhenyu
>>>>
>>>>> On Oct 18, 2018, at 12:01 PM, Gerard Visser <gvisser AT indiana.edu> wrote:
>>>>>
>>>>> hi Zhenyu,
>>>>> Sorry this is late...
>>>>> Cable mass by a weighing of 92 cm sample is *97 g/m* .
>>>>> I have to look for old costing info still but I wanted to get
>>>>> at lest this out this morning.
>>>>>
>>>>> Gerard
>>>>>
>>>>>
>>>>> On 10/17/2018 11:52 AM, Ye, Zhenyu wrote:
>>>>>> Hi Gerard,
>>>>>> Can you please tell me the mass of the cables, as well as the cost per
>>>>>> cable?
>>>>>> For the bulk cable, what would be the cost?
>>>>>> I am trying to put together the budget and cost, and will send
>>>>>> around and discuss with you once I have all the information.
>>>>>> Thanks,
>>>>>> Zhenyu
>>>>>>> On Oct 8, 2018, at 10:19 PM, Gerard Visser <gvisser AT indiana.edu>
>>>>>>> wrote:
>>>>>>>
>>>>>>> Hi Zhenyu,
>>>>>>> Ok if it is still TBD like that I think it is best to plan
>>>>>>> for 72 such cables, indeed.
>>>>>>> But this matter should be made more clear in fwd-upgrade
>>>>>>> meetings, e.g. we should have had it more clear in last weeks
>>>>>>> meeting. There is no problem from the readout side to go up to
>>>>>>> 864 chips, although the max rate will be a little lower I think
>>>>>>> we can still get what is needed by a combination of fewer
>>>>>>> timebins and more ARC-II/crates/PC's. However, everybody needs to
>>>>>>> be on the same page about all the options being considered, this
>>>>>>> must especially affect the MRI proposal and budget I would think.
>>>>>>> Please inform everyone more clearly what the range of options are.
>>>>>>> I will try to get a cable mass on wednesday. (The cable I
>>>>>>> have has a connector on it, but if I recall right it isn't really
>>>>>>> terminated, so I can remove it. But first I have to check that,
>>>>>>> and if it is really terminated I may not want to remove it, but
>>>>>>> rather try to estimate/account for the connector.) Tomorrow I will
>>>>>>> have to work from home, kids off school.
>>>>>>>
>>>>>>> - Gerard
>>>>>>>
>>>>>>>
>>>>>>> On 10/8/2018 9:20 PM, Ye, Zhenyu wrote:
>>>>>>>> Hi Gerard,
>>>>>>>> Thanks for the quick reply. The final number of APVs may be a
>>>>>>>> factor of
>>>>>>>> 1-3 of 288, so between 288-864 APVs (from the simulation 288
>>>>>>>> APVs gives an ok tracking resolution, but we may want to
>>>>>>>> increase the number of channels to see if we can improve the
>>>>>>>> performance). I will just tell John that there are 72 7.29mm
>>>>>>>> diameter cables, is that ok?
>>>>>>>>> On Oct 9, 2018, at 8:53 AM, Gerard Visser <gvisser AT indiana.edu>
>>>>>>>>> wrote:
>>>>>>>>>
>>>>>>>>> Hi Zhenyu,
>>>>>>>>> Yes I think that is a good assumption. Beware though, that
>>>>>>>>> was a custom made cable. If we will be able to afford it, I
>>>>>>>>> think that same sort of cable can be used. I'm pretty sure we
>>>>>>>>> do not have enough leftover bulk cable, but it could maybe work to
>>>>>>>>> re-use IST cables.
>>>>>>>>> I have a short piece here at Indiana and I measure the
>>>>>>>>> diameter is
>>>>>>>>> 7.29 mm. There is one cable per 12 APV group, that was 72
>>>>>>>>> cables in IST and will be 24 cables in FST. (BTW, this is a
>>>>>>>>> good time to ask to be sure, 288 APV is pretty well certain, is
>>>>>>>>> it?)
>>>>>>>>> I can get you a mass estimate on the purple cable too, but
>>>>>>>>> not today. Please let me know if that is needed.
>>>>>>>> Yes please send it to me when you get time.
>>>>>>>> Thanks,
>>>>>>>> Zhenyu
>>>>>>>>> Sincerely,
>>>>>>>>>
>>>>>>>>> Gerard
>>>>>>>>>
>>>>>>>>>
>>>>>>>>> On 10/8/2018 8:23 PM, Ye, Zhenyu wrote:
>>>>>>>>>> Hi Gerard,
>>>>>>>>>> For the FST cables inside the supporting cone, I think for now
>>>>>>>>>> we can assume they are of similar size as IST purple cables.
>>>>>>>>>> What do you think? I am away from the University this week and
>>>>>>>>>> thus can’t measure the cables by myself. Can you please tell
>>>>>>>>>> me what size of the IST purple cables is?
>>>>>>>>>> Thanks,
>>>>>>>>>> Zhenyu
>>> ...
>
> _______________________________________________
> Star-fst-l mailing list
> Star-fst-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/star-fst-l
-
Re: [Star-fst-l] Cost Estimate for Production FST Inner Signal Cables // Fwd: Re: integration of sTGC and Si,
Gerard Visser, 07/02/2019
-
Re: [Star-fst-l] Cost Estimate for Production FST Inner Signal Cables // Fwd: Re: integration of sTGC and Si,
Capotosto, Michael (CONTR), 07/02/2019
- Re: [Star-fst-l] Cost Estimate for Production FST Inner Signal Cables // Fwd: Re: integration of sTGC and Si, Zhenyu Ye, 07/02/2019
-
Re: [Star-fst-l] Cost Estimate for Production FST Inner Signal Cables // Fwd: Re: integration of sTGC and Si,
Gerard Visser, 07/02/2019
-
Re: [Star-fst-l] Cost Estimate for Production FST Inner Signal Cables // Fwd: Re: integration of sTGC and Si,
Capotosto, Michael (CONTR), 07/02/2019
-
Re: [Star-fst-l] Cost Estimate for Production FST Inner Signal Cables // Fwd: Re: integration of sTGC and Si,
Gerard Visser, 07/11/2019
- Re: [Star-fst-l] Cost Estimate for Production FST Inner Signal Cables // Fwd: Re: integration of sTGC and Si, Capotosto, Michael (CONTR), 07/11/2019
-
Re: [Star-fst-l] Cost Estimate for Production FST Inner Signal Cables // Fwd: Re: integration of sTGC and Si,
Gerard Visser, 07/11/2019
-
Re: [Star-fst-l] Cost Estimate for Production FST Inner Signal Cables // Fwd: Re: integration of sTGC and Si,
Capotosto, Michael (CONTR), 07/02/2019
-
Re: [Star-fst-l] Cost Estimate for Production FST Inner Signal Cables // Fwd: Re: integration of sTGC and Si,
Capotosto, Michael (CONTR), 07/02/2019
Archive powered by MHonArc 2.6.24.