Meeting minutes:
1. News: BNL approved funds to support FST. Contract with Fermilab SiDet for
FST module assembly has been put into BNL system since last week. According
to the SOW, we need to provide Fermilab drawings for FST modules, Silicon
sensors, hybrids and holding frames by this Sunday Sep 15.
2. DAQ: Tonko found 2 ARCII and at least 1 ARM are removed from the IST
crates. 1 ARCII and 1 ARM are in the lab in Physics building. Gerard and
Tonko will verify the status of the IST crates and readout boards next week.
Gerard and Paul will try to see if the IST slow control still works.
Prithwish and Yu will try to learn from them and provide assistance if
needed.
3. Shipping
Han-sheng/Yi: designed a box to ship FST modules.
4. Mechanical structure: EASTON will make the prototype mechanical structure
in October. AIDC will produce 10 prototype cooling tubes and joints in
October, and 55 in December. AIDC has done initial hybrid gluing to
mechanical structure by eye. The tolerance for Hybrid fabrication is 200
microns, and mechanical structure 100 microns.
5. Silicon sensors
Yi: Yi and Zhangbu visited NDL last week. The NDL staffs think they are able
to produce Silicon sensors but will take some time (~8 months) to find the
proper settings for implantation and polysilicon. A new NCKU Master student
will work on this.
6. Hybrid, T-board, and Inner signal cables
Qian: Nicomatics connectors for T-boards have arrived in China. The agency is
checking with the vendor to see if there is any issue with these connectors.
7. Simulation
Te-chuan: still working on FST GEANT modeling for cooling tube, and will add
APV chips and T-boards. He will report them next week.
Krishan: waiting for Daniel to provide the updated tracking code so that he
could study how efficiency depends on R.
Action items:
1. Prithwish will bring the ARCII and ARM back to STAR, and check exactly how
many ARMs are removed from the IST crates, and will try to look for the other
missing ARCII.
2. Flemming will find out from Rahul whether NOVEC has been delivered and if
so contact Gerrit for having a look at the IST rack.
3. Han-sheng will add 2 more screws to fix the FST module in the box, and
send Zhenyu the updated drawings and movie this Friday or Saturday.
4. We will check if we can use the PELICAN boxes which were used for shipping
IST modules for FST modules. Flemming found three of them at BNL.
5. Yi is working on the documentation of the mechanical structure. He has the
inputs from EASTON and AIDC in Chinese and will convert them to English.
6. Yi will discuss with AIDC for the precision they can achieve and whether
or not specific fixtures are needed for mounting hybrids to mechanical
structure
7. There are a number of studies to study the number of segmentation and
Z-locations that should be done once the tracking code is ready.
> On Sep 10, 2019, at 9:08 PM, Zhenyu Ye <yezhenyu2003 AT gmail.com> wrote:
>
> Dear all,
>
> We will have a meeting at 9am BNL time this Thursday Sep 12. The meeting
> agenda and bluejeans info can be found at
>
> https://drupal.star.bnl.gov/STAR/blog/yezhenyu/forward-silicon-tracker-weekly-meeting
>
> 1. News - All
> 2. Silicon sensor - Zhenyu Ye, Yi Yang
> 2. T-board, Hybrid, Inner Signal Cable - Jianing Dong, Michael Capotosto,
> Gerard Visser
> 3. Mechanical Structure - Yi Yang, Han-sheng Li
> 4. Simulation - Te-Chuan Huang, Krishan Gopal
>
> Best,
> Zhenyu
> _______________________________________________
> Star-fst-l mailing list
> Star-fst-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/star-fst-l
-
[Star-fst-l] Weekly FST meeting - 9/12/2019,
Zhenyu Ye, 09/10/2019
-
Re: [Star-fst-l] Weekly FST meeting - 9/12/2019,
Zhenyu Ye, 09/12/2019
-
Re: [Star-fst-l] Weekly FST meeting - 9/12/2019,
Han-Sheng Li, 09/13/2019
-
Re: [Star-fst-l] Weekly FST meeting - 9/12/2019,
Zhenyu Ye, 09/13/2019
- Re: [Star-fst-l] Weekly FST meeting - 9/12/2019, Han-Sheng Li, 09/13/2019
-
Re: [Star-fst-l] Weekly FST meeting - 9/12/2019,
Zhenyu Ye, 09/13/2019
-
Re: [Star-fst-l] Weekly FST meeting - 9/12/2019,
Han-Sheng Li, 09/13/2019
-
Re: [Star-fst-l] Weekly FST meeting - 9/12/2019,
Zhenyu Ye, 09/12/2019
Archive powered by MHonArc 2.6.24.