  • From: "Ye, Zhenyu" <yezhenyu AT uic.edu>
  • To: Aschenauer Elke-Caroline <elke AT bnl.gov>
  • Cc: "star-fst-l AT lists.bnl.gov" <star-fst-l AT lists.bnl.gov>
  • Subject: Re: [Star-fst-l] Quote from Hamamatsu on BNL Purchase of Production sensor
  • Date: Tue, 10 Mar 2020 17:10:44 +0000



> On Mar 10, 2020, at 12:04 PM, Aschenauer Elke-Caroline <elke AT bnl.gov> wrote:
>
> ah, super thanks this helps a lot. As we need to prepare al lthe paper work
> to order the sensors, is there a drop dead date by when you want us to
> order the sensors?

Since the estimated lead time is 5-5.5 months ARO, I think we’d better have
the order out by the end of June, assuming no change to the sensor design is
needed. We shall know if this is the case from the tests we are doing now
with the prototype modules.

Zhenyu

>
> Thanks elke
>
>> On Mar 10, 2020, at 13:03, Ye, Zhenyu <yezhenyu AT uic.edu> wrote:
>>
>> Hi Elke,
>>
>> The prices SDU had on their quote is without the import tax charged by
>> Chinese government.
>> If the sensors were to be purchased by SDU, they may need to pay this tax,
>> i.e. 20%.
>> Hope this helps.
>>
>> Zhenyu
>>
>>> On Mar 10, 2020, at 11:14 AM, Aschenauer Elke-Caroline <elke AT bnl.gov>
>>> wrote:
>>>
>>> Dear Zhenyu,
>>>
>>> question I thought that buying in the US would be 20% cheaper then if we
>>> buy in China, Is this not anymore true or do I misunderstand something.
>>>
>>> Cheers elke
>>>
>>>> On Mar 10, 2020, at 10:54, Ye, Zhenyu <yezhenyu AT uic.edu> wrote:
>>>>
>>>> I asked Hamamatsu to provide a quote for BNL purchase of the production
>>>> sensors. Their replies can be found at
>>>>
>>>> https://drupal.star.bnl.gov/STAR/blog/yezhenyu/forward-silicon-tracker-sensor
>>>>
>>>> under number 7: Hamamatsu Quote and lead-time estimate for BNL
>>>> production sensor.
>>>>
>>>> In summary, the lead time is 5-5.5 months ARO. The price is the same as
>>>> the SDU one, i.e. $278,400.
>>>>
>>>> Best,
>>>> Zhenyu
>>>>
>>>> _______________________________________________
>>>> Star-fst-l mailing list
>>>> Star-fst-l AT lists.bnl.gov
>>>> https://lists.bnl.gov/mailman/listinfo/star-fst-l
>>>
>>>
>>> ( `,_' )+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-
>>> ) `\ +
>>> / '. | Elke-Caroline Aschenauer (she/her/hers) =
>>> | `, -
>>> \,_ `-/ Brookhaven National Lab +
>>> ,&&&&&V Physics Dept., 25 Corona Road =
>>> ,&&&&&&&&: Bldg. 510 /2-195 Rocky Point, NY, -
>>> ,&&&&&&&&&&; 20 Pennsylvania Avenue 11778 +
>>> | |&&&&&&&;\ Upton, NY 11973 =
>>> | | :_) _ Tel.: 001-631-344-4769 Tel.: +1-631-569-4290 -
>>> | | ;--' | Cell-USA: +1-757-2565224 +
>>> '--' `-.--. | Cell-Europe: +49152220025211 =
>>> \_ | |—‘ -
>>> `-._\__/ Mail: elke AT bnl.gov elke.caroline AT me.com
>>> +
>>>
>>> +=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=
>>>
>>>
>>>
>>>
>>>
>>>
>>>
>>>
>>>
>>
>
>
> ( `,_' )+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-
> ) `\ +
> / '. | Elke-Caroline Aschenauer (she/her/hers) =
> | `, -
> \,_ `-/ Brookhaven National Lab +
> ,&&&&&V Physics Dept., 25 Corona Road =
> ,&&&&&&&&: Bldg. 510 /2-195 Rocky Point, NY, -
> ,&&&&&&&&&&; 20 Pennsylvania Avenue 11778 +
> | |&&&&&&&;\ Upton, NY 11973 =
> | | :_) _ Tel.: 001-631-344-4769 Tel.: +1-631-569-4290 -
> | | ;--' | Cell-USA: +1-757-2565224 +
> '--' `-.--. | Cell-Europe: +49152220025211 =
> \_ | |—‘ -
> `-._\__/ Mail: elke AT bnl.gov elke.caroline AT me.com +
>
> +=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=




Archive powered by MHonArc 2.6.24.

Top of Page