Elke, all,

under reasonable (?) assumptions (see below) the electronics is
still expected to be ready by Sep 1st:

* The following doesn't depend on us returning to the site
since we are simply waiting for the vendor and relying on
the dates it provided:

DEP/ADC assembled & delivered to BNL: 5/1 --> 6/15

* The following assumes we can begin to work on site on June 1st:

DEP/ADC fully tested: 6/15 --> 8/1
DAQ Receiver Boards installed:  4/1 --> 6/15

* The following assumes we will have access to the detector in August:

DEP system installed in STAR:  8/15  -> 8/15 (note no delay: taken from float)
FCS Electronics Commissioned:  9/1 --> 9/1 (note no delay: taken from float)

         -- Tonko






On Thu, Apr 30, 2020 at 8:49 AM Yi Yang <yiyang AT ncku.edu.tw> wrote:
Hi Zhenyu,

It looks good to me. Thanks a lot for summarizing this.

Cheers,
Yi

+++++++++++++++++++++++++++++++++++++++++++++++++++
Yi Yang, Associate Professor
Department of Physics
National Cheng Kung University
Tainan, 701 Taiwan
E-Mail: yiyang AT ncku.edu.tw
Tel: +886-6-2757575 ext.65237
Fax: +886-6-2747995
Group Web: http://phys.ncku.edu.tw/~yiyang
+++++++++++++++++++++++++++++++++++++++++++++++++++


On Wed, Apr 29, 2020 at 10:32 PM Ye, Zhenyu <yezhenyu AT uic.edu> wrote:
The milestones from F2F meeting (https://indico.bnl.gov/event/7773/) are in black, my guesstimate in red assuming

1) NCKU delivers at least 2 good mechanical structures with hybrids in 1st week of June
2) Fermilab reopens in the first week of June, 2020
3) No change in delivery time for the main items 

Please comment. 


Prototype assembly: 2/28/20 (+1mo) -> 6/30/2020
Module testing: 4/30/30 (+1 mo) -> 7/31/2020
Production (ordering): 5/31/20 (+1 mo) -> 8/31/2020
1st batch of Hybrids: 7/31/20 -> 10/31/2020
1st batch  of mechanical structure: 9/31/20 -> 12/31/2020
1st batch of sensors: 12/31/20 -> 2/28/2021
Assembly complete: 4/30/21 -> 6/30/2021
Supporting structure: 
Design and Fab: ?? Rahul  (9/31/20) -> 12/31/2020
Installation of modules on support: 6/15/21 -> 7/30/2021
Install detector into STAR: 7/15/21 -> 8/15/2021



Begin forwarded message:

From: Aschenauer Elke-Caroline via Star-fwd-upgrade-l <star-fwd-upgrade-l AT lists.bnl.gov>
Subject: [Star-fwd-upgrade-l] Important request
Date: April 28, 2020 at 10:47:31 PM CDT
Reply-To: Aschenauer Elke-Caroline <elke AT bnl.gov>, star-fwd-upgrade-l AT lists.bnl.gov

Dear All,

I need urgently some information from all of you so I can understand what can be done in the fall 2020 shutdown and in the following one.
Therefore I would like to get updates on all of your milestones, please use the information from the last face to face meetign and indicate how things moved.

I need this please separately for the Silicon, the sTGC, the FCS, the electronics (DEP and FEE), the slow-control, Trigger and Integration.

Gerard today the question for the EPD splitter came up, did you have a chance to talk with Tim about it?

Thanks elke



 ( `,_' )+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-
  )    `\                                                      +
 /    '. |        Elke-Caroline Aschenauer  (she/her/hers)      =
 |       `,                                                      -
  \,_  `-/        Brookhaven National Lab                         +
  ,&&&&&V         Physics Dept.,            25 Corona Road         =
 ,&&&&&&&&:       Bldg. 510 /2-195          Rocky Point, NY,        -
,&&&&&&&&&&;      20 Pennsylvania Avenue                 11778       +
|  |&&&&&&&;\     Upton, NY 11973                                     =
|  |       :_) _  Tel.:  001-631-344-4769   Tel.:   +1-631-569-4290    -
|  |       ;--' |                           Cell-USA:  +1-757-2565224   +
'--'   `-.--.   |                           Cell-Europe: +49152220025211 =
   \_    |  |—‘                                                           -
     `-._\__/     Mail: elke AT bnl.gov        elke.caroline AT me.com           +
            +=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=









_______________________________________________
Star-fwd-upgrade-l mailing list
Star-fwd-upgrade-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fwd-upgrade-l

_______________________________________________
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l
_______________________________________________
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l



Archive powered by MHonArc 2.6.24.

Top of Page