  • From: "Ye, Zhenyu" <yezhenyu AT uic.edu>
  • To: "star-fst-l AT lists.bnl.gov" <star-fst-l AT lists.bnl.gov>
  • Subject: [Star-fst-l] Fwd: [Star-fwd-upgrade-l] Important request
  • Date: Wed, 29 Apr 2020 14:32:34 +0000

The milestones from F2F meeting (https://indico.bnl.gov/event/7773/) are in black, my guesstimate in red assuming

1) NCKU delivers at least 2 good mechanical structures with hybrids in 1st week of June
2) Fermilab reopens in the first week of June, 2020
3) No change in delivery time for the main items 

Please comment. 


Prototype assembly: 2/28/20 (+1mo) -> 6/30/2020
Module testing: 4/30/30 (+1 mo) -> 7/31/2020
Production (ordering): 5/31/20 (+1 mo) -> 8/31/2020
1st batch of Hybrids: 7/31/20 -> 10/31/2020
1st batch  of mechanical structure: 9/31/20 -> 12/31/2020
1st batch of sensors: 12/31/20 -> 2/28/2021
Assembly complete: 4/30/21 -> 6/30/2021
Supporting structure: 
Design and Fab: ?? Rahul  (9/31/20) -> 12/31/2020
Installation of modules on support: 6/15/21 -> 7/30/2021
Install detector into STAR: 7/15/21 -> 8/15/2021



Begin forwarded message:

From: Aschenauer Elke-Caroline via Star-fwd-upgrade-l <star-fwd-upgrade-l AT lists.bnl.gov>
Subject: [Star-fwd-upgrade-l] Important request
Date: April 28, 2020 at 10:47:31 PM CDT
Reply-To: Aschenauer Elke-Caroline <elke AT bnl.gov>, star-fwd-upgrade-l AT lists.bnl.gov

Dear All,

I need urgently some information from all of you so I can understand what can be done in the fall 2020 shutdown and in the following one.
Therefore I would like to get updates on all of your milestones, please use the information from the last face to face meetign and indicate how things moved.

I need this please separately for the Silicon, the sTGC, the FCS, the electronics (DEP and FEE), the slow-control, Trigger and Integration.

Gerard today the question for the EPD splitter came up, did you have a chance to talk with Tim about it?

Thanks elke



 ( `,_' )+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-
  )    `\                                                      +
 /    '. |        Elke-Caroline Aschenauer  (she/her/hers)      =
 |       `,                                                      -
  \,_  `-/        Brookhaven National Lab                         +
  ,&&&&&V         Physics Dept.,            25 Corona Road         =
 ,&&&&&&&&:       Bldg. 510 /2-195          Rocky Point, NY,        -
,&&&&&&&&&&;      20 Pennsylvania Avenue                 11778       +
|  |&&&&&&&;\     Upton, NY 11973                                     =
|  |       :_) _  Tel.:  001-631-344-4769   Tel.:   +1-631-569-4290    -
|  |       ;--' |                           Cell-USA:  +1-757-2565224   +
'--'   `-.--.   |                           Cell-Europe: +49152220025211 =
   \_    |  |—‘                                                           -
     `-._\__/     Mail: elke AT bnl.gov        elke.caroline AT me.com           +
            +=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=-+=









_______________________________________________
Star-fwd-upgrade-l mailing list
Star-fwd-upgrade-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fwd-upgrade-l




Archive powered by MHonArc 2.6.24.

Top of Page