  • From: Zhenyu Ye <yezhenyu2003 AT gmail.com>
  • To: videbaek <videbaek AT bnl.gov>
  • Cc: star-fst-l AT lists.bnl.gov
  • Subject: Re: [Star-fst-l] FST session for the "F2F" meeting July 20-21
  • Date: Fri, 17 Jul 2020 17:36:43 -0500

On 2)
we tried two vendors for the prototype hybrids. I think we need to choose one
for production. We may also want to remind ourselves that we need to require
the thickness of the hybrid, which was done for one vendor but not the other.
Also if we decide SDU produce assemble the T-boards, what the QA/QC procedure
is.

Sent from my iPhone

> On Jul 17, 2020, at 5:17 PM, videbaek <videbaek AT bnl.gov> wrote:
>
> I think, in particular item 1 is important as it effects assembly -
> I am not sure 2. is critical as long it gets done
>
> In short let's add that talk.
>
> Flemming
>
>
>> On 2020-07-14 10:05, Ye, Zhenyu wrote:
>> Dear all,
>> The STAR Forward Upgrade “F2F" meeting will take place on Monday and
>> Tuesday July 20-21. A Drupal webpage for the meeting can be found at
>> https://drupal.star.bnl.gov/STAR/conference/timetable/talk/50911
>> Below is the proposed agenda for the FST session, currently scheduled
>> on July 20 Monday morning. The exact starting time and duration of
>> each talk is not yet fixed. I understand that Yi prefers for his stalk
>> to be after 10:30am. If anyone has any comment/constraint, please let
>> me know.
>> FST Mechanical Structure by Yi Yang (30’)
>> FST Prototype Assembly and Test by Xu Sun (20’)
>> FST Simulation by Shenghui Zhang (15’)
>> FST Integration and Cooling System by Rahul Sharma (25’)
>> FST Timeline, Milestones and Resources by Flemming Videbaek (25’)
>> Best,
>> Zhenyu
>> _______________________________________________
>> Star-fst-l mailing list
>> Star-fst-l AT lists.bnl.gov
>> https://lists.bnl.gov/mailman/listinfo/star-fst-l
>
> --
> Flemming Videbaek
> senior scientist
> videbaek @ bnl.gov
> Brookhaven National Lab
> Physics Department
> Bldg 510D
> Upton, NY 11973
>
> phone: 631-344-4106
> cell : 631-681-1596
> _______________________________________________
> Star-fst-l mailing list
> Star-fst-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/star-fst-l




Archive powered by MHonArc 2.6.24.

Top of Page