Hi Zhenyu,
I agree completely with what you are suggesting in terms of QA/QC `. As you probably recall I have brought it up several times.
On grey cables recall we used 72 for IST, and none were thrown out. All in the basement here at BNL. I think the main concern is the connector in terms of mechanical damage when they were pulled out and moved.
Flemming
On 2021-02-20 11:44, Ye, Zhenyu wrote:
Hi all,
We have encountered a few issues with cables (both inner purple and
outer grey cables) lately during the module production tests. Xu will
give a detailed report on Monday.
As a reminder, for the production purple cables/T-board assemblies,
SDU has mounted components on 10 T-boards, 2 of them are at NCKU for
hybrid fit testing, while the other 8 have been assembled with purple
cables by the company Mike works with (I will refer them as
pre-productioin purple cables below). SDU still has 40 more bare
T-boards waiting for testing results before mounting components and
sent to BNL for purple cable assembly. So in total I expect that we
will have 50 production purple cable/T-board assemblies, which I
thought were sufficient for use in the experiment (36) and as spares.
What worries me is the fraction of working purple cables seems to be
rather low in prototyping and in pre-production. For example, out of
the 8 pre-production purple cables, we have tried four at
UIC/Fermilab, and two of them have a problem (similar rate for
prototyping). I think we really need to do QC/QA for the purple cable
assembly, which I understand Mike has a QA plan but has not been
executed. With this fraction of good quality cables, I am also worried
that the number of good purple cable/T-board assemblies we end up
having is insufficient, and I am wondering if we should have more of
them produced.
The problem with the grey cable that Xu mentioned is so far an
isolated case, but we need to check the other grey cables we have to
make sure the ones we use in the experiment do not have a problem.
Mike, can you please remind me how many grey cables we have? (I think
we really should make an inventory of all the electronic components,
including the existing ARC, ARM, PPB, ABC, grey cables,
purple/T-board, how many we have, where they are and their status)
Best,
Zhenyu
_______________________________________________
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l
--
Flemming Videbaek
senior scientist
videbaek @ bnl.gov
Brookhaven National Lab
Physics Department
Bldg 510D
Upton, NY 11973
phone: 631-344-4106
cell : 631-681-1596
-
[Star-fst-l] Issues with cables,
Ye, Zhenyu, 02/20/2021
-
Re: [Star-fst-l] Issues with cables,
videbaek, 02/20/2021
- Re: [Star-fst-l] Issues with cables, Ye, Zhenyu, 02/20/2021
- Re: [Star-fst-l] Issues with cables, Visser, Gerard, 02/20/2021
-
Re: [Star-fst-l] Issues with cables,
videbaek, 02/20/2021
Archive powered by MHonArc 2.6.24.