- From: "Visser, Gerard" <gvisser AT indiana.edu>
- To: "Videbaek, Christian" <cvidebaek AT bnl.gov>, "star-fst-l AT lists.bnl.gov" <star-fst-l AT lists.bnl.gov>
- Subject: Re: [Star-fst-l] FST Grey Cable Pull
- Date: Mon, 2 Aug 2021 13:17:55 +0000
- The weight of the cables hanging vertically in the rack (going down from the crate) must mostly be supported with cable ties to the sidewalls of the rack. There should be no significant force on the cable connectors / ABC boards. Of course also please have enough slack there that any ABC board can be replaced without decabling everything.
- The cables going vertically past the rear of crates should be dressed off to the sidewalls of the rack sufficiently to enable removing the crate power supply box from the rear of the crate without decabling everything. Keep in mind that the PS box
may have to be replaced in a short access someday.
Sent: Friday, July 30, 2021 12:41 PM
To: star-fst-l AT lists.bnl.gov <star-fst-l AT lists.bnl.gov>
Cc: Soja, Robert <soja AT bnl.gov>
Subject: [Star-fst-l] FST Grey Cable Pull
Hi All,
The bulk of the cable pull is complete.
We ran the cables under the floor tiles rather than using the trays, to avoid the badly congested points where the trays meet the magnets.
I’ll send a drawing with the details around later today.
The cables still need to be dressed at both ends.
Zhenyu, Xu, and Gavin will take care of the connections at the rack, with slack cable going under the floor at the south edge of the platform.
I will dress what I can of the endcap cables.
Is it ok to connect the wires to the PPBs, or should we wait until the cooling lines have been installed?
Christian
-
Re: [Star-fst-l] FST Grey Cable Pull,
Visser, Gerard, 08/02/2021
-
Re: [Star-fst-l] FST Grey Cable Pull,
Gavin Wilks, 08/03/2021
- Re: [Star-fst-l] FST Grey Cable Pull, Gavin Wilks, 08/04/2021
-
Re: [Star-fst-l] FST Grey Cable Pull,
Gavin Wilks, 08/03/2021
Archive powered by MHonArc 2.6.24.