Skip to Content.
Sympa Menu

star-tpc-l - Re: [[Star-tpc-l] ] tpc meeting minutes 9/11/2025

star-tpc-l AT lists.bnl.gov

Subject: Star-tpc-l mailing list

List archive

Chronological Thread  
  • From: "Fisyak, Yuri V" <fisyak AT bnl.gov>
  • To: "Videbaek, Flemming" <videbaek AT bnl.gov>, Star-tpc L <Star-tpc-l AT lists.bnl.gov>
  • Subject: Re: [[Star-tpc-l] ] tpc meeting minutes 9/11/2025
  • Date: Fri, 12 Sep 2025 16:23:23 +0000

Hi Fleming, 
   one correction for FF cosmic in 2025  we have ~15 M triggers (not 50 M).  For RF we do have ~500 M.


                                                              Yuri Fisyak

STAR                                           Phone: +1 631 344 3913
Brookhaven National Laboratory  Fax:    +1 631 344 4206
510A/1-161
http://www.star.bnl.gov/~fisyak       E-mail:
fisyak AT bnl.gov

 

 

From: star-tpc-l-request AT lists.bnl.gov <star-tpc-l-request AT lists.bnl.gov> on behalf of videbaek <videbaek AT bnl.gov>
Date: Friday, September 12, 2025 at 12:20 PM
To: Star-tpc L <Star-tpc-l AT lists.bnl.gov>
Subject: [[Star-tpc-l] ] tpc meeting minutes 9/11/2025




TPC meeting 9/11/2025
Present:Alexei, Yuri, Jim, Gen and Flemming
Hardware:
Work done to prepare for restart of run today.
Gas system ok – flowas has been tuned and is stable. Laser repair
finished both east and west are now bright.
TPC blower -condenser had to be restarted, it was noticed late that it
was not on. Are the any alarm on this – other that temperature rise?
Electronics
Tim and Tonko has changed several board and reprogrammed many RDO. At
time of meeting not quite complete, but on 9/12 several TPX RDOs were
brought back.
Software
Gene:
De/Dx calibration complete for some BES data sets- ready for production
Yuri:
Looker for response for laser runs with 0 field and half field to
determine hit error
Notice degradation in dp/p from two trck matching with cosmics from
previous run to run 25  1.5% to a little above 2%. Considers cluster
finder, may have to tune TPCRS .
AOB: we have plenty of cosmics from FF 50M triggers and RFF 500 M
trigger. Need data for ½ field  RF and F. Can be done during run for
reverse field. Discuss this with JH who under stands the priority to
have this done , and discussed procedures for duing this as it involves
changing filed and turning detertors (at least FFEs) off/on and again
off/on. Estime need a known ‘machichne down period of at least 3-4 hours
for this to be done.


--
Flemming Videbaek
senior scientist, emeritus
videbaek @ bnl.gov
Brookhaven National Lab
Physics Department
Bldg 510D
Upton, NY 11973

phone: 631-344-4106
cell     :  631-681-1596



Archive powered by MHonArc 2.6.24.

Top of Page