[Usatlas-hllhc-l2deputymgmt-nsf-l] NSF BCPs going forward
- From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
- To: "Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF BCPs going forward
- Date: Mon, 22 Jun 2020 12:40:32 +0200
Hello all,
A reminder that the NSF MREFC is now baselined, ie strict EVMS observance is required. One important point in that is that you can only do a BCP for work that is *> 2 months in the future*. There are, of course, exceptions. See figure attached. But there is no more changing the past beyond our usual reconciliations.
Best,
Gustaaf
Attachment:
Screen Shot 2020-06-22 at 12.36.53 PM.png
Description: PNG image
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] NSF BCPs going forward,
Gustaaf Brooijmans, 06/22/2020
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF BCPs going forward, Gustaaf Brooijmans, 06/22/2020
Archive powered by MHonArc 2.6.24.