Skip to Content.
Sympa Menu

usatlas-hllhc-l2deputymgmt-nsf-l - Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF BCPs going forward

usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List

List archive

Chronological Thread  
  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF BCPs going forward
  • Date: Mon, 22 Jun 2020 13:33:44 +0200


I should add that none of this applies to covid. For delays incurred because of that, we'll be able to make retroactive changes.

On 6/22/20 12:40 PM, Gustaaf Brooijmans wrote:

Hello all,

A reminder that the NSF MREFC is now baselined, ie strict EVMS observance is required.  One important point in that is that you can only do a BCP for work that is *> 2 months in the future*.  There are, of course, exceptions.  See figure attached.  But there is no more changing the past beyond our usual reconciliations.

Best,

Gustaaf