usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List
List archive
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF BCPs going forward
- From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
- To: usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF BCPs going forward
- Date: Mon, 22 Jun 2020 13:33:44 +0200
I should add that none of this applies to covid. For delays incurred because of that, we'll be able to make retroactive changes.
On 6/22/20 12:40 PM, Gustaaf Brooijmans wrote:
Hello all,
A reminder that the NSF MREFC is now baselined, ie strict EVMS observance is required. One important point in that is that you can only do a BCP for work that is *> 2 months in the future*. There are, of course, exceptions. See figure attached. But there is no more changing the past beyond our usual reconciliations.
Best,
Gustaaf
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] NSF BCPs going forward,
Gustaaf Brooijmans, 06/22/2020
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] NSF BCPs going forward, Gustaaf Brooijmans, 06/22/2020