usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List
List archive
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] 2021-06-15 Directors Review for NSF MREFC Annual review - Tuts.pptx
- From: Michael Tuts <tuts AT pmtuts.net>
- To: John Parsons <parsons AT nevis.columbia.edu>, "Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>, "us-atlas-hllhc-pmgmt-l AT lists.bnl.gov" <us-atlas-hllhc-pmgmt-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] 2021-06-15 Directors Review for NSF MREFC Annual review - Tuts.pptx
- Date: Sun, 13 Jun 2021 00:07:26 +0000
Hi John,
Thanks for the comments ... will have a look.
Cheers, Mike
-----Original Message-----
From: John Parsons <parsons AT nevis.columbia.edu>
Sent: Saturday, June 12, 2021 7:37 PM
To: Michael Tuts <tuts AT pmtuts.net>;
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov;
us-atlas-hllhc-pmgmt-l AT lists.bnl.gov
Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] 2021-06-15 Directors Review
for NSF MREFC Annual review - Tuts.pptx
Hi Mike,
I give a few comments below.
John
p. 3 - put DoE scope in different color scheme, to separate it more clearly?
(I do this in LAr)
p. 5 - not the best org. chart to show, since most of the PL for operations
need to be at CERN so there are fewer US people. More relevant (and more US
people) would be to show HL-LHC org chart?
p. 16 (and elsewhere) - while I don't mind directing the focus elsewhere, I
am just pointing out that the Columbia LAr spending never shows up in such
reports since we are not a SUBcontract
p. 17 - we have "COVID Actuals" and "COVID BCPs", which (as has been widely
discussed) don't agree precisely. Which do you mean by "current COVID cost
to date"?
p. 21 - plot is very confusing (at least to me)
p. 23 - I would add "university closures" at the front of the list of COVID
impacts, since we were all shut down for at least 3 months, right when the
MREFC started; particularly terrible timing!
On 6/12/21 3:53 PM, Michael Tuts wrote:
> Hi All,
>
> My draft talk. Comments are always welcome.
>
> Thanks, Mike
>
>
>
>
> _______________________________________________
> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-
> l
>
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!X0BdUz-ez69RqmjemuDklnQYX_9YP-D7H0abrrHpHh7TQLqjaj4hwIBXV_UWMCdZ3LAloO2Vsj0u2EakZMr2FbXgTgzN$
______________________________________________________________________
-
[Usatlas-hllhc-l2deputymgmt-nsf-l] 2021-06-15 Directors Review for NSF MREFC Annual review - Tuts.pptx,
Michael Tuts, 06/12/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] 2021-06-15 Directors Review for NSF MREFC Annual review - Tuts.pptx,
John Parsons, 06/12/2021
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] 2021-06-15 Directors Review for NSF MREFC Annual review - Tuts.pptx, Michael Tuts, 06/12/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] 2021-06-15 Directors Review for NSF MREFC Annual review - Tuts.pptx,
John Parsons, 06/12/2021
Archive powered by MHonArc 2.6.24.