  • From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
  • To: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
  • Subject: [Usatlas-hllhc-l2deputymgmt-nsf-l] April variance reports - comments
  • Date: Mon, 23 May 2022 11:30:02 +0200


Hello all,

Thanks for filing the variance reports on time. A few small comments (if no
comments the report looks good to me):


-6.6.4: I would suggest to add as corrective action “This will be corrected
at NSF rebaseline.”

-6.6.5: please remove all sentences related to cost variance - reporting on
cost varaince is not requested this month.

-6.8 and 6.8.2 are missing

-6.8.3: "due to missing international partners”? What does that mean? The
impact statement is a copy of the explanation; I guess a copy-paste mistake...

-6.9.2 is missing

Best,

Gustaaf