Hello all,
Thanks for filing the variance reports on time. A few small comments (if no
comments the report looks good to me):
-6.6.4: I would suggest to add as corrective action “This will be corrected
at NSF rebaseline.”
-6.6.5: please remove all sentences related to cost variance - reporting on
cost varaince is not requested this month.
-6.8 and 6.8.2 are missing
-6.8.3: "due to missing international partners”? What does that mean? The
impact statement is a copy of the explanation; I guess a copy-paste mistake...
-6.9.2 is missing
Best,
Gustaaf